3'-0" drilld pier no soil unit price, North Carolina
Low bidders on NCDOT contracts carried a median of $1,450.00 per LF for item 8105620000-E, 3'-0" drilld pier no soil, over the 24 months to 20 OCT 2026, across 4 low bids. Half of all 24 bids fell between $1,072.61 and $2,292.50.
- Owner
- North Carolina DOT
- Item
- 8105620000-E
- Unit
- LF
- Latest letting
- 18 AUG 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2013 | 25 | 25 | $1,196.22 | 120 | $1,198.11 |
| 2014 | 10 | 10 | $1,128.50 | 51 | $1,355.00 |
| 2015 | 4 | 4 | $1,155.00 | 30 | $1,235.00 |
| 2016 | 3 | 3 | $1,205.00 | 17 | $1,230.00 |
| 2017 | 2 | 2 | $519.00 | 17 | $1,100.00 |
| 2018 | 5 | 5 | $1,000.00 | 29 | $1,100.00 |
| 2019 | 2 | 2 | $1,575.00 | 12 | $1,200.00 |
| 2020 | 2 | 2 | $898.77 | 18 | $1,076.93 |
| 2021 | 2 | 2 | $1,296.50 | 10 | $1,169.09 |
| 2022 | 1 | 1 | $1,300.00 | 4 | $2,175.00 |
| 2024 | 1 | 1 | $3,271.00 | 4 | $3,435.50 |
| 2025 | 2 | 2 | $1,600.00 | 9 | $2,000.00 |
| 2026 | 2 | 2 | $1,245.00 | 15 | $1,500.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Guilford | 5 | $1,925.00 | 27 | $1,250.00 |
| Granville | 3 | $1,700.00 | 21 | $1,500.00 |
Countys with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 12 to 33 | 15 | $1,485.00 |
| 33 to 45 | 15 | $1,400.00 |
| 46 to 56 | 15 | $796.58 |
| 59 to 228 | 16 | $994.40 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 18 AUG 2026 | C204877 | Rutherford | 45 | $790.00 | $929.38 | 8 | R E BURNS & SONS CO INC | NCDOT |
| 17 FEB 2026 | C204936 | Alamance | 111.40 | $1,700.00 | $1,669.15 | 7 | KEMP SIGMON CONSTRUCTION CO INC | NCDOT |
| 16 SEP 2025 | C204971 | Guilford | 108 | $2,000.00 | $2,290.00 | 3 | BLYTHE CONSTRUCTION INC | NCDOT |
| 18 FEB 2025 | C204883 | Rutherford | 36 | $1,200.00 | $1,419.79 | 6 | KEMP SIGMON CONSTRUCTION CO INC | NCDOT |
| 28 MAY 2024 | C204411 | Haywood | 22 | $3,271.00 | $3,435.50 | 4 | WHALEY CONSTRUCTION, LLC. | NCDOT |
| 19 APR 2022 | C204484 | Madison | 44 | $1,300.00 | $2,175.00 | 4 | DELLINGER INC | NCDOT |
| 16 NOV 2021 | C204682 | Ashe | 43 | $1,430.00 | $990.00 | 2 | JAMES R VANNOY & SONS CONSTRUCTION COMPANY INC | NCDOT |
| 19 JAN 2021 | C204487 | Wilkes | 48 | $1,163.00 | $1,169.09 | 8 | EASTERN STRUCTURES LLC | NCDOT |
| 15 DEC 2020 | C204486 | Wilkes | 53 | $1,117.55 | $1,036.32 | 9 | JAMES R VANNOY & SONS CONSTRUCTION COMPANY INC | NCDOT |
| 15 DEC 2020 | C204516 | Iredell | 84 | $680.00 | $1,169.65 | 9 | R. E. BURNS & SONS CO., INC. | NCDOT |
| 18 JUN 2019 | C204428 | Franklin | 12 | $1,650.00 | $1,487.35 | 7 | FSC II LLC DBA FRED SMITH COMPANY | NCDOT |
| 16 APR 2019 | C204325 | Vance | 55 | $1,500.00 | $1,050.00 | 5 | NATIONAL BRIDGE BUILDERS LLC | NCDOT |
| 15 MAY 2018 | C204097 | Wake, Franklin | 38 | $1,600.00 | $1,368.50 | 6 | NATIONAL BRIDGE BUILDERS LLC | NCDOT |
| 15 MAY 2018 | C203790 | Anson | 63 | $100.00 | $865.00 | 7 | NATIONAL BRIDGE BUILDERS LLC | NCDOT |
| 20 FEB 2018 | C204069 | Wake | 75 | $1,060.00 | $1,060.00 | 7 | FLATIRON CONSTRUCTORS INC | NCDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.
How these prices were read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.