4'-0" drilld pier no soil unit price, North Carolina
Low bidders on NCDOT contracts carried a median of $2,267.00 per LF for item 8105660000-E, 4'-0" drilld pier no soil, over the 24 months to 20 OCT 2026, across 5 low bids. Half of all 34 bids fell between $1,384.87 and $2,255.25.
- Owner
- North Carolina DOT
- Item
- 8105660000-E
- Unit
- LF
- Latest letting
- 21 JUL 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2013 | 4 | 4 | $1,625.00 | 25 | $1,400.00 |
| 2014 | 4 | 4 | $1,565.00 | 32 | $1,807.28 |
| 2015 | 5 | 5 | $1,490.00 | 37 | $1,188.00 |
| 2016 | 2 | 2 | $1,175.00 | 9 | $1,400.00 |
| 2017 | 4 | 4 | $1,467.50 | 27 | $1,250.00 |
| 2018 | 4 | 4 | $1,304.86 | 22 | $1,650.00 |
| 2019 | 2 | 2 | $1,530.26 | 13 | $1,540.00 |
| 2021 | 3 | 3 | $1,040.00 | 11 | $943.00 |
| 2022 | 4 | 4 | $1,491.76 | 19 | $1,600.00 |
| 2023 | 6 | 6 | $1,650.00 | 29 | $1,570.00 |
| 2024 | 3 | 3 | $2,701.83 | 22 | $1,888.13 |
| 2025 | 1 | 1 | $2,544.41 | 8 | $1,597.87 |
| 2026 | 3 | 3 | $2,267.00 | 15 | $2,188.79 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Cabarrus | 6 | $1,450.00 | 32 | $1,325.00 |
| Guilford | 4 | $1,253.62 | 27 | $1,600.00 |
| Forsyth | 3 | $2,544.41 | 21 | $1,608.16 |
| Rockingham | 4 | $2,538.19 | 21 | $2,100.00 |
| Jackson | 3 | $1,880.00 | 20 | $2,081.18 |
| Wake | 3 | $100.00 | 18 | $930.00 |
Countys with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 16 to 40 | 11 | $1,685.00 |
| 43 to 68 | 11 | $1,383.52 |
| 72 to 116 | 11 | $1,875.00 |
| 124 to 704 | 12 | $1,188.38 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 21 JUL 2026 | C205194 | Rockingham | 33 | $2,749.81 | $2,749.81 | 5 | SMITH-ROWE, LLC | NCDOT |
| 16 JUN 2026 | C205186 | Rockingham | 47.90 | $2,267.00 | $1,975.00 | 6 | W C ENGLISH INCORPORATED | NCDOT |
| 19 MAY 2026 | C204733 | Yadkin | 40 | $2,048.36 | $2,118.57 | 4 | BLYTHE CONSTRUCTION INC | NCDOT |
| 17 JUN 2025 | C205041 | Forsyth | 72 | $2,544.41 | $1,597.87 | 8 | SMITH-ROWE, LLC | NCDOT |
| 17 DEC 2024 | C204969 | Anson | 99 | $1,233.53 | $1,500.00 | 11 | SANFORD CONTRACTORS INC | NCDOT |
| 28 MAY 2024 | C204762 | Caswell | 93.40 | $2,701.83 | $1,743.00 | 6 | SMITH-ROWE, LLC | NCDOT |
| 16 JAN 2024 | C204828 | Jackson | 52 | $2,810.00 | $2,548.00 | 5 | OWLE CONSTRUCTION LLC | NCDOT |
| 18 JUL 2023 | C204851 | Cleveland | 183.40 | $1,600.00 | $2,050.00 | 4 | AMES CONSTRUCTION INC | NCDOT |
| 16 MAY 2023 | C204763 | Rockingham | 33 | $2,395.39 | $2,395.39 | 3 | SMITH-ROWE, LLC | NCDOT |
| 16 MAY 2023 | C204716 | Burke | 187 | $1,000.00 | $1,700.00 | 4 | MOUNTAIN CREEK CONTRACTORS INC | NCDOT |
| 18 APR 2023 | C204793 | Rockingham | 104.10 | $2,681.00 | $1,700.00 | 7 | W C ENGLISH INCORPORATED | NCDOT |
| 18 APR 2023 | C204741 | Cabarrus | 165 | $1,700.00 | $1,345.62 | 4 | DANE CONSTRUCTION INC | NCDOT |
| 17 JAN 2023 | C204769 | Caswell | 81 | $1,223.10 | $1,223.10 | 7 | SMITH-ROWE, LLC | NCDOT |
| 15 NOV 2022 | C204554 | Wake | 54 | $100.00 | $2,405.00 | 6 | FSC II LLC DBA FRED SMITH COMPANY | NCDOT |
| 16 AUG 2022 | C204714 | Cabarrus | 218 | $1,600.00 | $1,425.00 | 5 | DANE CONSTRUCTION INC | NCDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.
How these prices were read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.