3'-6" drilld pier no soil unit price, North Carolina
Low bidders on NCDOT contracts carried a median of $2,092.07 per LF for item 8105640000-E, 3'-6" drilld pier no soil, over the 24 months to 20 OCT 2026, across 8 low bids. Half of all 49 bids fell between $1,500.00 and $2,206.61.
- Owner
- North Carolina DOT
- Item
- 8105640000-E
- Unit
- LF
- Latest letting
- 22 JAN 2026
$2,092.07Low bidder's median, per LF
$2,000.00Median of all bids, per LF
8Contracts in the window
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2013 | 6 | 6 | $1,287.50 | 33 | $1,550.00 |
| 2014 | 4 | 4 | $1,040.50 | 34 | $1,115.00 |
| 2015 | 7 | 7 | $1,268.00 | 48 | $1,271.50 |
| 2016 | 8 | 8 | $1,200.00 | 54 | $1,101.99 |
| 2017 | 3 | 3 | $1,400.00 | 18 | $1,393.03 |
| 2018 | 5 | 5 | $1,186.00 | 29 | $1,220.00 |
| 2019 | 1 | 1 | $2,300.00 | 5 | $2,300.00 |
| 2020 | 1 | 1 | $2,142.29 | 8 | $2,081.91 |
| 2021 | 3 | 3 | $1,466.00 | 22 | $1,912.11 |
| 2022 | 6 | 6 | $1,477.82 | 39 | $1,600.00 |
| 2023 | 4 | 4 | $1,647.18 | 22 | $1,588.26 |
| 2024 | 5 | 5 | $2,258.00 | 32 | $1,987.50 |
| 2025 | 6 | 6 | $1,915.88 | 42 | $1,841.82 |
| 2026 | 2 | 2 | $2,411.81 | 7 | $2,623.61 |
Bid prices as published, not adjusted for inflation.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 22 JAN 2026 | C205145 | Yancey | 222 | $2,623.61 | $2,623.61 | 1 | ARCHER WESTERN CONSTRUCTION LLC | NCDOT |
| 20 JAN 2026 | C205132 | Cleveland | 28 | $2,200.00 | $2,657.50 | 6 | BLYTHE CONSTRUCTION INC | NCDOT |
| 16 DEC 2025 | C205018 | Rockingham | 60 | $2,184.13 | $2,092.07 | 6 | SMITH-ROWE, LLC | NCDOT |
| 16 DEC 2025 | C205071 | Rockingham | 154.60 | $2,206.61 | $2,050.00 | 3 | SMITH-ROWE, LLC | NCDOT |
| 19 AUG 2025 | C204832 | Nash, Halifax | 46 | $985.00 | $985.00 | 7 | S T WOOTEN CORPORATION | NCDOT |
| 19 AUG 2025 | C204991 | Mecklenburg | 48 | $2,000.00 | $1,331.99 | 6 | BLYTHE DEVELOPMENT LLC | NCDOT |
| 20 MAY 2025 | C205032 | Chatham | 140.80 | $800.00 | $1,862.91 | 12 | FSC II LLC DBA FRED SMITH COMPANY | NCDOT |
| 15 APR 2025 | C205061 | Guilford | 25.50 | $1,831.77 | $2,229.43 | 8 | DELLINGER INC | NCDOT |
| 20 AUG 2024 | C204925 | Haywood | 125 | $2,258.00 | $3,475.00 | 7 | NHM CONSTRUCTORS INC | NCDOT |
| 18 JUN 2024 | C204929 | Rockingham | 58.20 | $1,823.94 | $1,831.97 | 4 | SMITH-ROWE, LLC | NCDOT |
| 28 MAY 2024 | C204913 | Forsyth | 51 | $3,467.64 | $3,467.64 | 5 | APAC ATLANTIC INC SMITH ROWE LLC JV | NCDOT |
| 19 MAR 2024 | C204876 | Rockingham | 15.60 | $1,417.32 | $1,230.00 | 9 | SMITH-ROWE, LLC | NCDOT |
| 20 FEB 2024 | C204792 | Johnston | 30 | $2,500.00 | $1,870.00 | 7 | S T WOOTEN CORPORATION | NCDOT |
| 19 DEC 2023 | C204823 | Haywood | 364 | $1,950.00 | $1,634.40 | 4 | BUCHANAN AND SONS INC | NCDOT |
| 15 AUG 2023 | C204815 | Davidson | 120 | $1,755.37 | $1,713.68 | 6 | SMITH-ROWE, LLC | NCDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.
How these prices were read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.