12" conduit, type b, as per plan unit price, Ohio
Low bidders on ODOT contracts carried a median of $128.00 per FT for item 611E04401, 12" conduit, type b, as per plan, over the 24 months to 12 NOV 2026, across 17 low bids. Half of all 51 bids fell between $96.50 and $195.00.
- Owner
- Ohio DOT
- Item
- 611E04401
- Unit
- FT
- Latest letting
- 07 MAY 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 5 | 6 | $108.75 | 20 | $114.62 |
| 2021 | 7 | 7 | $120.00 | 24 | $122.50 |
| 2022 | 4 | 4 | $137.00 | 18 | $142.50 |
| 2023 | 8 | 8 | $170.00 | 29 | $150.00 |
| 2024 | 2 | 2 | $134.50 | 6 | $146.50 |
| 2025 | 7 | 8 | $134.50 | 20 | $148.50 |
| 2026 | 8 | 9 | $111.50 | 31 | $112.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (FT) | Low bids | Low-bid median |
|---|---|---|
| 30 to 55 | 4 | $352.50 |
| 88 to 161 | 4 | $128.00 |
| 404 to 472 | 4 | $100.75 |
| 541 to 1,532 | 5 | $94.77 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 07 MAY 2026 | 260226 | ALL | 602 | $85.00 | $98.00 | 3 | FENSON CONTRACTING LLC | ODOT |
| 07 MAY 2026 | 260240 | HUR | 32 | $210.00 | $210.00 | 3 | RIETSCHLIN CONSTRUCTION INC | ODOT |
| 23 APR 2026 | 260216 | VAN | 161 | $128.00 | $125.50 | 2 | VERNON NAGEL INC | ODOT |
| 23 APR 2026 | 260216 | VAN | 88 | $128.00 | $119.00 | 2 | VERNON NAGEL INC | ODOT |
| 09 APR 2026 | 260177 | LIC | 404 | $111.50 | $218.25 | 2 | SHELLY COMPANY | ODOT |
| 12 MAR 2026 | 268001 | WYA | 472 | $90.00 | $120.00 | 10 | EAGLE BRIDGE CO | ODOT |
| 26 FEB 2026 | 260041 | LIC | 90 | $240.00 | $192.50 | 2 | KOKOSING CONSTRUCTION COMPANY INC | ODOT |
| 29 JAN 2026 | 260002 | HEN | 541 | $94.77 | $94.77 | 3 | E S WAGNER - VERNON NAGEL JOINT VENTURE | ODOT |
| 15 JAN 2026 | 260022 | LUC | 472 | $84.40 | $89.70 | 4 | VERNON NAGEL INC | ODOT |
| 18 DEC 2025 | 250610 | CUY | 34 | $495.00 | $485.00 | 5 | GREAT LAKES CONSTRUCTION CO | ODOT |
| 09 OCT 2025 | 250404 | HAM | 425 | $135.00 | $126.45 | 3 | GREAT LAKES CONSTRUCTION CO | ODOT |
| 15 MAY 2025 | 250238 | HAM | 159 | $118.86 | $122.29 | 2 | JOHN R JURGENSEN COMPANY | ODOT |
| 24 APR 2025 | 250230 | TUS | 897 | $134.00 | $134.00 | 1 | SHELLY & SANDS INC | ODOT |
| 27 MAR 2025 | 250166 | TUS | 30 | $116.00 | $135.00 | 3 | STANLEY MILLER CONSTRUCTION COMPANY | ODOT |
| 20 MAR 2025 | 250078 | CUY | 953 | $80.00 | $90.00 | 2 | GREAT LAKES CONSTRUCTION CO | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.