Low bidders on ODOT contracts carried a median of $33.25 per FT for item 611E02600, 8" conduit, type f, over the 24 months to 12 NOV 2026, across 15 low bids. Half of all 64 bids fell between $20.00 and $50.00.
- Owner
- Ohio DOT
- Item
- 611E02600
- Unit
- FT
- Latest letting
- 12 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 9 | 10 | $18.00 | 32 | $15.38 |
| 2021 | 12 | 12 | $13.25 | 51 | $22.19 |
| 2022 | 9 | 9 | $25.00 | 33 | $26.25 |
| 2023 | 9 | 9 | $49.00 | 28 | $48.30 |
| 2024 | 5 | 5 | $30.00 | 17 | $30.00 |
| 2025 | 8 | 8 | $20.00 | 40 | $32.00 |
| 2026 | 7 | 7 | $47.00 | 24 | $37.50 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (FT) | Low bids | Low-bid median |
|---|---|---|
| 8 to 10 | 3 | $34.00 |
| 15 to 40 | 4 | $14.00 |
| 50 to 50 | 4 | $42.20 |
| 100 to 272 | 4 | $38.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 12 NOV 2026 | 260512 | TRU | 15 | $10.00 | $25.00 | 5 | A P O'HORO COMPANY | ODOT |
| 01 OCT 2026 | 260405 | DEL | 8 | $85.00 | $69.45 | 3 | SHELLY & SANDS INC | ODOT |
| 01 OCT 2026 | 260433 | PUT | 10 | $34.00 | $42.19 | 6 | FENSON CONTRACTING LLC | ODOT |
| 17 SEP 2026 | 260416 | WIL | 40 | $45.00 | $45.00 | 3 | GEDDIS PAVING & EXCAVATING INC | ODOT |
| 11 JUN 2026 | 260286 | FUL | 50 | $51.16 | $33.00 | 3 | ECLIPSE CO LLC | ODOT |
| 09 APR 2026 | 260147 | DEL | 50 | $65.00 | $40.00 | 3 | COMPLETE GENERAL CONSTRUCTION COMPANY | ODOT |
| 09 APR 2026 | 260175 | GAL | 100 | $47.00 | $47.00 | 1 | ALLARD EXCAVATION LLC | ODOT |
| 15 MAY 2025 | 250153 | FAI | 100 | $22.00 | $42.64 | 4 | SHELLY & SANDS INC | ODOT |
| 10 APR 2025 | 250196 | NOB | 25 | $8.00 | $26.50 | 6 | J & J BRIDGE COMPANY INC | ODOT |
| 10 APR 2025 | 250197 | PRE | 50 | $33.25 | $34.87 | 6 | DOUBLE JAY CONSTRUCTION INC | ODOT |
| 27 MAR 2025 | 250079 | HEN | 200 | $30.00 | $30.00 | 3 | E S WAGNER COMPANY | ODOT |
| 27 MAR 2025 | 250163 | PER | 25 | $18.00 | $18.00 | 9 | AXIS CIVIL CONSTRUCTION LLC | ODOT |
| 13 FEB 2025 | 254006 | ALL | 272 | $60.00 | $37.00 | 4 | ADVANCED EXCAVATING & DEMOLITION LLC | ODOT |
| 30 JAN 2025 | 250050 | HAN | 50 | $8.00 | $25.00 | 5 | EAGLE BRIDGE CO | ODOT |
| 30 JAN 2025 | 254005 | SEN | 8 | $15.00 | $25.00 | 3 | GREAT LAKES DEMOLITION COMPANY | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.