9" non-reinforced concrete pavement, class qc 1P unit price, Ohio
Low bidders on ODOT contracts carried a median of $104.00 per SY for item 452E13010, 9" non-reinforced concrete pavement, class qc 1p, over the 24 months to 12 NOV 2026, across 19 low bids. Half of all 64 bids fell between $101.40 and $135.00.
- Owner
- Ohio DOT
- Item
- 452E13010
- Unit
- SY
- Latest letting
- 01 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 5 | 5 | $72.00 | 17 | $78.15 |
| 2021 | 4 | 5 | $81.25 | 31 | $78.00 |
| 2022 | 8 | 8 | $89.00 | 32 | $94.83 |
| 2023 | 7 | 7 | $91.00 | 21 | $105.00 |
| 2024 | 7 | 7 | $100.00 | 34 | $112.00 |
| 2025 | 12 | 12 | $101.50 | 42 | $113.50 |
| 2026 | 4 | 4 | $107.25 | 12 | $118.50 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 45 to 285 | 4 | $149.75 |
| 286 to 585 | 5 | $100.00 |
| 624 to 900 | 5 | $104.00 |
| 915 to 12,909 | 5 | $98.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 01 OCT 2026 | 268018 | DEL | 367 | $110.00 | $125.00 | 4 | DOUBLE Z CONSTRUCTION COMPANY | ODOT |
| 23 APR 2026 | 260198 | FAI | 856 | $104.00 | $111.25 | 4 | SHELLY COMPANY | ODOT |
| 26 MAR 2026 | 260152 | HAS | 72 | $195.00 | $212.50 | 2 | SHELLY & SANDS INC | ODOT |
| 26 MAR 2026 | 260166 | ALL | 285 | $104.50 | $113.25 | 2 | R D JONES EXCAVATING INC | ODOT |
| 04 DEC 2025 | 250559 | HOC | 338 | $95.00 | $115.00 | 5 | COMPLETE GENERAL CONSTRUCTION COMPANY | ODOT |
| 04 DEC 2025 | 254030 | GEA | 637 | $133.68 | $133.68 | 3 | MADEX CONSTRUCTION CO | ODOT |
| 13 NOV 2025 | 250521 | FAI | 915 | $110.00 | $110.00 | 7 | SHELLY & SANDS INC | ODOT |
| 22 MAY 2025 | 258009 | AUG | 45 | $102.00 | $150.00 | 5 | PERRAM ELECTRIC INC | ODOT |
| 15 MAY 2025 | 250238 | HAM | 209 | $318.11 | $221.56 | 2 | JOHN R JURGENSEN COMPANY | ODOT |
| 24 APR 2025 | 250209 | ALL | 286 | $99.90 | $113.50 | 6 | R D JONES EXCAVATING INC | ODOT |
| 24 APR 2025 | 250210 | ATB | 3,202 | $98.00 | $98.00 | 1 | CATTS CONSTRUCTION INC | ODOT |
| 17 APR 2025 | 250151 | FRA | 624 | $86.00 | $95.00 | 4 | COMPLETE GENERAL CONSTRUCTION COMPANY | ODOT |
| 27 MAR 2025 | 250079 | HEN | 12,909 | $79.55 | $80.00 | 3 | E S WAGNER COMPANY | ODOT |
| 27 FEB 2025 | 250076 | FRA | 9,974 | $125.93 | $125.93 | 1 | SHELLY & SANDS INC | ODOT |
| 30 JAN 2025 | 250002 | LAK | 475 | $105.00 | $103.27 | 2 | GREAT LAKES CONSTRUCTION CO | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.