Rock excavation unit price, Ohio
Low bidders on ODOT contracts carried a median of $75.00 per CY for item 503E31100, rock excavation, over the 24 months to 12 NOV 2026, across 13 low bids. Half of all 60 bids fell between $70.00 and $162.50.
- Owner
- Ohio DOT
- Item
- 503E31100
- Unit
- CY
- Latest letting
- 29 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 2 | 3 | $110.00 | 20 | $110.00 |
| 2021 | 8 | 10 | $82.50 | 61 | $75.00 |
| 2022 | 10 | 11 | $75.00 | 59 | $75.00 |
| 2023 | 6 | 6 | $102.50 | 26 | $95.00 |
| 2024 | 6 | 6 | $138.97 | 32 | $100.00 |
| 2025 | 8 | 8 | $112.50 | 43 | $120.00 |
| 2026 | 3 | 4 | $52.50 | 15 | $115.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 3 to 17 | 3 | $160.00 |
| 20 to 54 | 3 | $52.00 |
| 56 to 64 | 3 | $95.00 |
| 85 to 814 | 4 | $105.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 29 OCT 2026 | 260454 | ADA | 17 | $75.00 | $157.00 | 5 | D G M INC | ODOT |
| 29 OCT 2026 | 260454 | ADA | 54 | $50.00 | $137.00 | 5 | D G M INC | ODOT |
| 01 OCT 2026 | 260427 | LAW | 20 | $52.00 | $70.00 | 4 | ALLARD EXCAVATION LLC | ODOT |
| 09 APR 2026 | 260175 | GAL | 42 | $53.00 | $53.00 | 1 | ALLARD EXCAVATION LLC | ODOT |
| 13 NOV 2025 | 250526 | HIG | 85 | $60.00 | $120.00 | 8 | D G M INC | ODOT |
| 13 NOV 2025 | 250544 | JAC | 56 | $70.00 | $157.15 | 7 | D G M INC | ODOT |
| 22 MAY 2025 | 258011 | ATH | 64 | $95.00 | $80.00 | 5 | ALAN STONE CO INC | ODOT |
| 27 FEB 2025 | 250128 | MEG | 814 | $35.00 | $52.25 | 6 | KOKOSING CONSTRUCTION COMPANY INC | ODOT |
| 27 FEB 2025 | 250129 | MOE | 96 | $200.00 | $147.50 | 4 | R C CONSTRUCTION COMPANY AND SON INC | ODOT |
| 13 FEB 2025 | 250096 | MOE | 3 | $610.00 | $700.00 | 3 | ALAN STONE CO INC | ODOT |
| 13 FEB 2025 | 250104 | VIN | 60 | $130.00 | $105.00 | 6 | ALAN STONE CO INC | ODOT |
| 30 JAN 2025 | 254003 | BRO | 6 | $160.00 | $130.00 | 4 | ALAN STONE CO INC | ODOT |
| 14 NOV 2024 | 240510 | CUY | 146 | $150.00 | $150.00 | 2 | BLACK HORSE BRIDGE CONSTRUCTION INC | ODOT |
| 08 AUG 2024 | 240393 | SCI | 55 | $134.00 | $100.00 | 7 | SUNESIS CONSTRUCTION CO | ODOT |
| 11 JUL 2024 | 244017 | HAS | 532 | $143.94 | $100.00 | 4 | BCC OHIO INC | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.