Anchor assembly removed, type a unit price, Ohio

Low bidders on ODOT contracts carried a median of $295.00 per EACH for item 202E42000, anchor assembly removed, type a, over the 24 months to 12 NOV 2026, across 56 low bids. Half of all 165 bids fell between $250.00 and $365.00.

Owner
Ohio DOT
Item
202E42000
Unit
EACH
Latest letting
12 NOV 2026
$295.00Low bidder's median, per EACH
$300.00Median of all bids, per EACH
56Contracts in the window

By year of letting

Anchor assembly removed, type a, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20204040$285.00191$295.00
20212727$275.00113$285.00
20223838$290.00135$300.00
20232929$300.0096$303.36
20243333$335.00123$325.00
20252727$295.0076$295.00
20262323$320.0065$325.00
Anchor assembly removed, type a, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Anchor assembly removed, type a, ODOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
ASD5$200.0012$207.50
District 55$295.0012$307.50
District 93$200.0011$250.00
WAY3$295.008$204.00
WIL3$320.004$322.50
Anchor assembly removed, type a, ODOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Anchor assembly removed, type a, ODOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 214$345.00
2 to 414$272.50
4 to 1014$297.50
11 to 14814$260.00
Anchor assembly removed, type a, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Anchor assembly removed, type a
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
12 NOV 2026260489ASD23$200.00$200.002SHELLY & SANDS INCODOT
12 NOV 2026260506LUC4$325.00$262.502SHELLY COMPANYODOT
29 OCT 2026260454ADA8$250.00$350.005D G M INCODOT
29 OCT 2026260455ASD16$200.00$200.002KOKOSING CONSTRUCTION COMPANY INCODOT
15 OCT 2026260464WOO7$320.00$320.002GERKEN PAVING INCODOT
01 OCT 2026260433PUT14$325.00$276.506FENSON CONTRACTING LLCODOT
01 OCT 2026260446District 931$200.00$225.004PDK CONSTRUCTION INCODOT
27 AUG 2026260391CUY1$400.00$450.006OHIO CONCRETE MAINTENANCE LLCODOT
13 AUG 2026260345CUY4$325.00$325.004GREAT LAKES CONSTRUCTION COODOT
13 AUG 2026260373WIL11$320.00$320.001GERKEN PAVING INCODOT
16 JUL 2026260336District 510$295.00$335.002LAKE ERIE CONSTRUCTION COMPANYODOT
21 MAY 2026260270LAW2$1,000.00$800.003ALAN STONE CO INCODOT
07 MAY 2026260247ROS4$450.00$475.004AXIS CIVIL CONSTRUCTION LLCODOT
07 MAY 2026260254WIL7$325.00$325.001GERKEN PAVING INCODOT
07 MAY 2026260261MIA4$150.00$150.002BRUMBAUGH CONSTRUCTION INCODOT
Latest ODOT contracts carrying Anchor assembly removed, type a

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy