Anchor assembly removed, type b unit price, Ohio

Low bidders on ODOT contracts carried a median of $135.00 per EACH for item 202E42050, anchor assembly removed, type b, over the 24 months to 12 NOV 2026, across 31 low bids. Half of all 84 bids fell between $125.00 and $200.00.

Owner
Ohio DOT
Item
202E42050
Unit
EACH
Latest letting
12 NOV 2026
$135.00Low bidder's median, per EACH
$145.00Median of all bids, per EACH
31Contracts in the window

By year of letting

Anchor assembly removed, type b, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20201515$125.0049$125.00
202155$125.0016$150.00
20221314$142.5041$125.00
202355$125.0012$135.00
20241111$120.0028$128.12
20251515$125.0046$133.12
20261515$150.0033$150.00
Anchor assembly removed, type b, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Anchor assembly removed, type b, ODOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
ERI3$115.509$115.50
RIC3$130.007$130.00
District 53$120.007$125.00
HEN3$152.256$250.00
Anchor assembly removed, type b, ODOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Anchor assembly removed, type b, ODOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 17$135.00
1 to 28$156.12
2 to 48$143.85
4 to 118$122.50
Anchor assembly removed, type b, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Anchor assembly removed, type b
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
12 NOV 2026260489ASD3$200.00$200.002SHELLY & SANDS INCODOT
12 NOV 2026260506LUC2$135.00$167.502SHELLY COMPANYODOT
17 SEP 2026260400ASD2$100.00$117.502SHELLY & SANDS INCODOT
16 JUL 2026260331ROS1$300.00$650.002SHELLY & SANDS INCODOT
16 JUL 2026260336District 55$120.00$160.002LAKE ERIE CONSTRUCTION COMPANYODOT
25 JUN 2026260308CUY1$200.00$200.003KOKOSING CONSTRUCTION COMPANY INCODOT
11 JUN 2026268011HEN1$152.25$249.812EIUS COMPANYODOT
23 APR 2026260197ERI3$137.70$136.352ERIE BLACKTOP INCODOT
26 MAR 2026260146District 121$200.00$200.001LAKE ERIE CONSTRUCTION COMPANYODOT
19 FEB 2026260095SAN1$141.75$135.003ERIE BLACKTOP INCODOT
29 JAN 2026260002HEN4$252.53$250.003E S WAGNER - VERNON NAGEL JOINT VENTUREODOT
29 JAN 2026260073District 91$125.00$125.003PDK CONSTRUCTION INCODOT
15 JAN 2026260014HAM4$150.00$150.002JOHN R JURGENSEN COMPANYODOT
15 JAN 2026260015HAM3$150.00$150.002BARRETT PAVING MATERIALS INCODOT
15 JAN 2026260026RIC6$125.00$125.002SHELLY & SANDS INCODOT
Latest ODOT contracts carrying Anchor assembly removed, type b

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy