Bridge terminal assembly removed unit price, Ohio

Low bidders on ODOT contracts carried a median of $100.00 per EACH for item 202E47000, bridge terminal assembly removed, over the 24 months to 12 NOV 2026, across 103 low bids. Half of all 277 bids fell between $75.00 and $200.00.

Owner
Ohio DOT
Item
202E47000
Unit
EACH
Latest letting
12 NOV 2026
$100.00Low bidder's median, per EACH
$110.00Median of all bids, per EACH
101Contracts in the window

By year of letting

Bridge terminal assembly removed, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20204847$95.00174$100.00
20213939$75.00138$79.19
20224246$77.50148$75.00
20235051$75.00149$85.00
20243838$87.50107$104.00
20255153$100.00151$100.00
20264242$107.50109$137.50
Bridge terminal assembly removed, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Bridge terminal assembly removed, ODOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
CUY7$95.0022$110.00
LOR4$155.0016$110.00
ASD6$87.3815$99.75
HAM6$200.0015$200.00
District 56$82.5014$97.50
MED3$175.0013$175.00
ERI4$77.8812$77.88
District 93$190.0011$150.00
BUT4$90.0011$137.50
FRA3$125.009$125.00
HEN4$99.888$175.00
GRE3$125.007$125.00
Bridge terminal assembly removed, ODOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Bridge terminal assembly removed, ODOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 325$150.00
3 to 426$90.00
4 to 1026$78.38
10 to 6826$110.00
Bridge terminal assembly removed, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Bridge terminal assembly removed
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
12 NOV 2026260489ASD12$200.00$200.002SHELLY & SANDS INCODOT
12 NOV 2026260506LUC4$85.00$142.502SHELLY COMPANYODOT
12 NOV 2026260513BEL1$150.00$150.001SHELLY & SANDS INCODOT
29 OCT 2026260417LOR3$110.00$110.007CORROSION RESISTANCE LTDODOT
29 OCT 2026260455ASD20$75.00$75.002KOKOSING CONSTRUCTION COMPANY INCODOT
29 OCT 2026260467LAW1$93.00$516.502ALLARD EXCAVATION LLCODOT
29 OCT 2026260471MOT2$150.00$481.235EAGLE BRIDGE COODOT
29 OCT 2026260474WAR16$200.00$200.002BARRETT PAVING MATERIALS INCODOT
01 OCT 2026260434RIC12$200.00$200.002KOKOSING CONSTRUCTION COMPANY INCODOT
01 OCT 2026260446District 94$190.00$150.004PDK CONSTRUCTION INCODOT
01 OCT 2026260449HEN1$100.00$100.002E S WAGNER - VERNON NAGEL JOINT VENTUREODOT
17 SEP 2026260400ASD14$100.00$87.502SHELLY & SANDS INCODOT
27 AUG 2026260379BUT8$105.00$150.005BCC OHIO INCODOT
27 AUG 2026260391CUY3$95.00$97.506OHIO CONCRETE MAINTENANCE LLCODOT
13 AUG 2026260345CUY3$95.00$95.004GREAT LAKES CONSTRUCTION COODOT
Latest ODOT contracts carrying Bridge terminal assembly removed

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.