Manhole removed unit price, Ohio

Low bidders on ODOT contracts carried a median of $750.00 per EACH for item 202E58000, manhole removed, over the 24 months to 12 NOV 2026, across 57 low bids. Half of all 209 bids fell between $600.00 and $1,261.47.

Owner
Ohio DOT
Item
202E58000
Unit
EACH
Latest letting
12 NOV 2026
$750.00Low bidder's median, per EACH
$840.00Median of all bids, per EACH
57Contracts in the window

By year of letting

Manhole removed, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20202020$505.0083$700.00
20212731$600.00168$620.00
20221617$750.0063$750.00
20232830$673.5098$819.80
20242121$800.0073$800.00
20252828$720.0097$818.21
20262828$800.00110$850.00
Manhole removed, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Manhole removed, ODOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
HAM7$1,261.4724$1,286.97
CUY6$800.0020$820.00
LIC3$1,000.0015$800.00
SUM3$1,050.009$850.00
FRA3$574.007$900.00
Manhole removed, ODOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Manhole removed, ODOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 114$730.00
1 to 214$725.21
2 to 414$670.54
5 to 4215$850.00
Manhole removed, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Manhole removed
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
12 NOV 2026260521GUE2$400.00$640.568SHELLY & SANDS INCODOT
29 OCT 2026260399CUY8$800.00$750.004TRI-MOR CORPODOT
29 OCT 2026260456COL2$600.00$647.502SHELLY & SANDS INCODOT
29 OCT 2026260461HAM2$641.08$675.005SUNESIS CONSTRUCTION COODOT
29 OCT 2026260468MAH5$877.00$1,063.504SHELLY & SANDS INCODOT
15 OCT 2026260484GAL2$600.00$500.003ALLARD EXCAVATION LLCODOT
08 OCT 2026260398HAM22$1,507.24$1,507.241JOHN R JURGENSEN COMPANYODOT
27 AUG 2026260381CLE1$750.43$976.655AXIS CIVIL CONSTRUCTION LLCODOT
27 AUG 2026260382CUY2$1,794.00$1,794.003PERK COMPANY INCODOT
13 AUG 2026260345CUY2$1,200.00$737.504GREAT LAKES CONSTRUCTION COODOT
13 AUG 2026260364KNO5$1,050.00$1,275.004COMPLETE GENERAL CONSTRUCTION COMPANYODOT
13 AUG 2026260372SUM1$1,050.00$900.002PERRAM ELECTRIC INCODOT
30 JUL 2026268015PRE15$758.52$804.266R B JERGENS CONTRACTORS INCODOT
11 JUN 2026260287FUL2$1,100.00$335.003MILLER BROS CONST INCODOT
21 MAY 2026260265DEF2$600.00$625.006KOKOSING CONSTRUCTION COMPANY INCODOT
Latest ODOT contracts carrying Manhole removed

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy