Special - pipe cleanout, 24" and under unit price, Ohio

Low bidders on ODOT contracts carried a median of $32.50 per FT for item 202E70110, special - pipe cleanout, 24" and under, over the 24 months to 12 NOV 2026, across 36 low bids. Half of all 129 bids fell between $20.00 and $63.00.

Owner
Ohio DOT
Item
202E70110
Unit
FT
Latest letting
12 NOV 2026
$32.50Low bidder's median, per FT
$32.00Median of all bids, per FT
35Contracts in the window

By year of letting

Special - pipe cleanout, 24" and under, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20201719$25.0096$21.55
20211515$18.5589$20.00
20221414$25.2542$25.00
20231616$33.8344$25.50
20241212$43.0738$43.00
20252020$36.6265$33.00
20261314$31.2157$35.00
Special - pipe cleanout, 24" and under, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Special - pipe cleanout, 24" and under, ODOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
CUY5$18.5023$29.50
FRA3$19.0012$19.50
HAM4$127.1211$60.00
ATB3$50.0011$50.00
Special - pipe cleanout, 24" and under, ODOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Special - pipe cleanout, 24" and under, ODOT: low bidder's median by quantity band
Quantity (FT)Low bidsLow-bid median
10 to 579$67.57
60 to 1509$92.00
174 to 2609$19.00
300 to 4,4009$14.00
Special - pipe cleanout, 24" and under, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Special - pipe cleanout, 24" and under
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
12 NOV 2026260524WAR250$35.00$35.007PRUS CONSTRUCTION COMPANYODOT
29 OCT 2026260461HAM207$27.42$40.005SUNESIS CONSTRUCTION COODOT
29 OCT 2026260477ATB260$5.00$20.003KARVO COMPANIES INCODOT
01 OCT 2026260405DEL331$25.00$25.003SHELLY & SANDS INCODOT
27 AUG 2026260381CLE57$60.00$42.005AXIS CIVIL CONSTRUCTION LLCODOT
11 JUN 2026260282ATB32$90.00$53.004A P O'HORO COMPANYODOT
11 JUN 2026260282ATB60$50.00$55.004A P O'HORO COMPANYODOT
21 MAY 2026264014WAS118$200.00$95.004R C CONSTRUCTION COMPANY AND SON INCODOT
07 MAY 2026260240HUR50$22.00$100.003RIETSCHLIN CONSTRUCTION INCODOT
23 APR 2026260203HUR100$4.50$10.003MARK HAYNES CONSTRUCTION INCODOT
23 APR 2026260221FRA300$40.00$28.502COMPLETE GENERAL CONSTRUCTION COMPANYODOT
29 JAN 2026260064POR150$25.00$20.002KARVO COMPANIES INCODOT
29 JAN 2026260069ASD97$103.10$74.003OHIO CONCRETE MAINTENANCE LLCODOT
15 JAN 2026260010CUY190$5.00$28.009TRI-MOR CORPODOT
18 DEC 2025250610CUY600$18.50$63.005GREAT LAKES CONSTRUCTION COODOT
Latest ODOT contracts carrying Special - pipe cleanout, 24" and under

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy