Special - pipe cleanout over 48" unit price, Ohio
Low bidders on ODOT contracts carried a median of $56.00 per FT for item 202E70130, special - pipe cleanout over 48", over the 24 months to 12 NOV 2026, across 29 low bids. Half of all 109 bids fell between $47.28 and $130.00.
- Owner
- Ohio DOT
- Item
- 202E70130
- Unit
- FT
- Latest letting
- 13 AUG 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 17 | 18 | $36.25 | 106 | $54.50 |
| 2021 | 16 | 28 | $17.19 | 178 | $40.00 |
| 2022 | 16 | 16 | $35.50 | 57 | $47.44 |
| 2023 | 17 | 20 | $33.00 | 72 | $43.50 |
| 2024 | 20 | 19 | $50.97 | 73 | $82.59 |
| 2025 | 13 | 16 | $43.50 | 60 | $87.50 |
| 2026 | 8 | 8 | $61.00 | 26 | $63.50 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| HAM | 4 | $71.63 | 15 | $117.40 |
| WAY | 5 | $42.00 | 15 | $48.90 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (FT) | Low bids | Low-bid median |
|---|---|---|
| 45 to 100 | 7 | $120.00 |
| 111 to 213 | 7 | $59.00 |
| 228 to 393 | 7 | $42.00 |
| 398 to 1,444 | 8 | $55.48 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 13 AUG 2026 | 260353 | LOR | 448 | $140.00 | $85.88 | 2 | GREAT LAKES CONSTRUCTION CO | ODOT |
| 13 AUG 2026 | 260369 | RIC | 355 | $72.00 | $244.17 | 3 | PROSHOT CONCRETE INC | ODOT |
| 30 JUL 2026 | 260349 | HAM | 427 | $92.30 | $224.26 | 5 | MADEX CONSTRUCTION CO | ODOT |
| 11 JUN 2026 | 260291 | SCI | 436 | $62.00 | $63.50 | 2 | TURN-KEY TUNNELING INC | ODOT |
| 07 MAY 2026 | 260251 | MOT | 1,444 | $60.00 | $45.00 | 2 | JOHN R JURGENSEN COMPANY | ODOT |
| 07 MAY 2026 | 264012 | RIC | 79 | $48.36 | $73.18 | 2 | EIUS COMPANY | ODOT |
| 19 FEB 2026 | 260102 | CUY | 45 | $35.00 | $51.65 | 7 | V3 CONSTRUCTION GROUP LTD | ODOT |
| 19 FEB 2026 | 264006 | WAY | 115 | $59.00 | $30.00 | 3 | CRAWFORD CONSTRUCTION COMPANY INC | ODOT |
| 13 NOV 2025 | 250517 | CLE | 68 | $28.46 | $100.00 | 10 | BCC OHIO INC | ODOT |
| 09 OCT 2025 | 250458 | CLI | 186 | $71.37 | $185.69 | 2 | MADEX CONSTRUCTION CO | ODOT |
| 25 SEP 2025 | 254024 | GRE | 98 | $150.00 | $115.95 | 2 | AXIS CIVIL CONSTRUCTION LLC | ODOT |
| 11 SEP 2025 | 250405 | BUT | 393 | $45.00 | $182.75 | 4 | TEMPLE & TEMPLE EXCAVATING & PAVING INC | ODOT |
| 28 AUG 2025 | 254021 | CLE | 172 | $200.00 | $85.00 | 3 | AXIS CIVIL CONSTRUCTION LLC | ODOT |
| 14 AUG 2025 | 250384 | WAY | 140 | $42.00 | $48.90 | 3 | OHIO CONCRETE MAINTENANCE LLC | ODOT |
| 14 AUG 2025 | 250384 | WAY | 198 | $42.00 | $48.90 | 3 | OHIO CONCRETE MAINTENANCE LLC | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.