Valve box removed unit price, Ohio

Low bidders on ODOT contracts carried a median of $195.00 per EACH for item 202E75610, valve box removed, over the 24 months to 12 NOV 2026, across 16 low bids. Half of all 73 bids fell between $175.00 and $400.00.

Owner
Ohio DOT
Item
202E75610
Unit
EACH
Latest letting
12 NOV 2026
$195.00Low bidder's median, per EACH
$250.00Median of all bids, per EACH
16Contracts in the window

By year of letting

Valve box removed, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202033$114.0018$167.50
20211111$165.0059$165.00
202277$200.0030$183.50
20231110$249.0032$199.00
202466$237.5025$250.00
202577$190.0029$297.00
202688$210.0038$225.00
Valve box removed, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By quantity

Valve box removed, ODOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 14$362.50
1 to 24$165.00
3 to 54$210.00
7 to 124$167.07
Valve box removed, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Valve box removed
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
12 NOV 2026260521GUE3$220.00$197.508SHELLY & SANDS INCODOT
12 NOV 2026260524WAR2$155.00$170.007PRUS CONSTRUCTION COMPANYODOT
15 OCT 2026260484GAL1$148.00$390.003ALLARD EXCAVATION LLCODOT
25 JUN 2026268012VAN1$500.00$525.003PERRAM ELECTRIC INCODOT
07 MAY 2026260239HAR1$225.00$250.003EAGLE BRIDGE COODOT
23 APR 2026260198FAI4$365.00$382.504SHELLY COMPANYODOT
26 MAR 2026260121HAM7$169.14$257.074SUNESIS CONSTRUCTION COODOT
29 JAN 2026260066PRE4$200.00$199.506BRUMBAUGH CONSTRUCTION INCODOT
28 AUG 2025250398TRU7$75.00$250.006KIRILA CONTRACTORS INCODOT
14 AUG 2025250383WAS1$1,100.00$450.008MCVOYT CONSTRUCTION COMPANY INCODOT
22 MAY 2025258009AUG2$250.00$330.005PERRAM ELECTRIC INCODOT
27 MAR 2025250159HAR2$175.00$236.002HELMS AND SONS EXCAVATINGODOT
20 MAR 2025250078CUY12$165.00$292.502GREAT LAKES CONSTRUCTION COODOT
27 FEB 2025250076FRA8$276.00$276.001SHELLY & SANDS INCODOT
30 JAN 2025250047FAI5$190.00$250.005SHELLY COMPANYODOT
Latest ODOT contracts carrying Valve box removed

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy