Fence removed unit price, Ohio

Low bidders on ODOT contracts carried a median of $5.00 per FT for item 202E75000, fence removed, over the 24 months to 12 NOV 2026, across 147 low bids. Half of all 587 bids fell between $4.00 and $10.00.

Owner
Ohio DOT
Item
202E75000
Unit
FT
Latest letting
12 NOV 2026
$5.00Low bidder's median, per FT
$5.25Median of all bids, per FT
147Contracts in the window

By year of letting

Fence removed, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20207778$4.00464$4.00
20219091$3.29507$4.00
20226668$5.00284$5.00
20236769$5.00273$5.00
20246464$5.00286$5.00
20258080$5.00324$6.00
20266262$5.00242$5.00
Fence removed, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Fence removed, ODOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
CUY11$10.0038$10.00
HAM10$7.4732$7.12
BEL5$4.4024$5.00
LIC3$4.5023$10.00
ROS5$3.9021$5.00
PIK3$4.0020$7.50
DEL4$6.6720$7.50
FRA7$5.0019$6.50
WAY5$7.5015$4.50
RIC3$2.5814$7.17
HAS3$4.0014$5.00
MED3$10.0013$7.00
Fence removed, ODOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Fence removed, ODOT: low bidder's median by quantity band
Quantity (FT)Low bidsLow-bid median
8 to 10436$10.00
104 to 24037$6.00
240 to 63437$4.33
635 to 50,64437$4.00
Fence removed, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Fence removed
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
12 NOV 2026260491BEL1,270$2.20$3.218SAORSA CONSTRUCTION OHIO, INC.ODOT
12 NOV 2026260492CLA375$15.00$10.003FILLMORE CONSTRUCTIONODOT
12 NOV 2026260521GUE410$2.75$4.548SHELLY & SANDS INCODOT
12 NOV 2026260524WAR1,984$2.75$5.007PRUS CONSTRUCTION COMPANYODOT
29 OCT 2026260399CUY462$10.00$10.004TRI-MOR CORPODOT
29 OCT 2026260417LOR400$4.00$4.007CORROSION RESISTANCE LTDODOT
29 OCT 2026260456COL410$3.00$3.502SHELLY & SANDS INCODOT
29 OCT 2026260477ATB300$3.50$3.503KARVO COMPANIES INCODOT
29 OCT 2026268021JEF2,178$5.25$5.253BUDS INCODOT
15 OCT 2026260484GAL110$2.00$4.503ALLARD EXCAVATION LLCODOT
08 OCT 2026260398HAM10,719$12.03$12.031JOHN R JURGENSEN COMPANYODOT
01 OCT 2026260405DEL3,508$3.75$3.753SHELLY & SANDS INCODOT
01 OCT 2026260419BEL475$3.00$6.624MARUCCI & GAFFNEY EXCAVATING COODOT
01 OCT 2026260427LAW508$2.00$5.004ALLARD EXCAVATION LLCODOT
01 OCT 2026260429MED163$11.00$9.006FECHKO EXCAVATING LLCODOT
Latest ODOT contracts carrying Fence removed

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy