Catch basin removed unit price, Ohio

Low bidders on ODOT contracts carried a median of $500.00 per EACH for item 202E58100, catch basin removed, over the 24 months to 12 NOV 2026, across 175 low bids. Half of all 658 bids fell between $440.25 and $873.75.

Owner
Ohio DOT
Item
202E58100
Unit
EACH
Latest letting
12 NOV 2026
$500.00Low bidder's median, per EACH
$573.30Median of all bids, per EACH
172Contracts in the window

By year of letting

Catch basin removed, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20208688$364.75424$392.25
202197104$378.57510$400.00
20228690$405.50332$450.00
20237376$461.00266$522.38
20246465$500.00233$580.07
20258182$485.00324$550.00
20268587$588.00312$600.00
Catch basin removed, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Catch basin removed, ODOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
CUY12$690.0048$770.00
HAM12$735.0040$755.41
LIC7$750.0032$572.50
TRU5$350.0029$431.75
DEL5$400.0023$550.00
FRA8$570.0021$613.00
BEL5$400.0020$600.00
MOT3$508.1917$513.30
TUS5$700.0016$662.50
ALL4$457.5015$400.00
WAR3$250.0015$561.02
FAI3$300.0015$600.00
Catch basin removed, ODOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Catch basin removed, ODOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 143$500.00
1 to 344$525.00
4 to 844$558.86
8 to 7944$500.00
Catch basin removed, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Catch basin removed
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
12 NOV 2026260459FUL1$415.00$700.005TOLEDO CAISSON CORPORATIONODOT
12 NOV 2026260502HAM1$4,900.00$2,975.004ALAN STONE CO INCODOT
12 NOV 2026260524WAR3$250.00$500.007PRUS CONSTRUCTION COMPANYODOT
29 OCT 2026260399CUY26$800.00$787.504TRI-MOR CORPODOT
29 OCT 2026260468MAH12$900.00$1,050.004SHELLY & SANDS INCODOT
29 OCT 2026260477ATB1$500.00$950.003KARVO COMPANIES INCODOT
15 OCT 2026260484GAL11$250.00$300.003ALLARD EXCAVATION LLCODOT
08 OCT 2026260398HAM40$1,012.94$1,012.941JOHN R JURGENSEN COMPANYODOT
01 OCT 2026260405DEL4$930.00$571.603SHELLY & SANDS INCODOT
01 OCT 2026260430MOT5$508.19$529.108R B JERGENS CONTRACTORS INCODOT
01 OCT 2026260432POR4$1,000.00$1,000.004SHELLY & SANDS INCODOT
01 OCT 2026260433PUT8$550.00$525.006FENSON CONTRACTING LLCODOT
01 OCT 2026260438VIN1$1,000.00$1,000.007FILLMORE CONSTRUCTIONODOT
01 OCT 2026260439WAR4$500.00$1,002.363FILLMORE CONSTRUCTIONODOT
17 SEP 2026260402CUY3$500.00$601.655CATTS CONSTRUCTION INCODOT
Latest ODOT contracts carrying Catch basin removed

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy