Bike lane symbol marking unit price, Ohio
Low bidders on ODOT contracts carried a median of $315.00 per EACH for item 644E01630, bike lane symbol marking, over the 24 months to 12 NOV 2026, across 9 low bids. Half of all 28 bids fell between $275.00 and $550.00.
- Owner
- Ohio DOT
- Item
- 644E01630
- Unit
- EACH
- Latest letting
- 17 SEP 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 12 | 12 | $375.00 | 54 | $375.00 |
| 2021 | 8 | 7 | $325.00 | 30 | $346.40 |
| 2022 | 8 | 8 | $340.00 | 31 | $328.00 |
| 2023 | 5 | 5 | $450.00 | 12 | $388.00 |
| 2024 | 5 | 5 | $360.00 | 11 | $360.00 |
| 2025 | 5 | 5 | $575.00 | 20 | $510.00 |
| 2026 | 4 | 4 | $265.00 | 8 | $307.50 |
Bid prices as published, not adjusted for inflation.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 17 SEP 2026 | 260410 | MAR | 26 | $230.00 | $290.00 | 2 | SHELLY & SANDS INC | ODOT |
| 07 MAY 2026 | 260232 | CUY | 1 | $315.00 | $315.00 | 3 | PERK COMPANY INC | ODOT |
| 09 APR 2026 | 260168 | ATB | 12 | $300.00 | $300.00 | 1 | UNION INDUSTRIAL CONTRACTORS INC | ODOT |
| 26 MAR 2026 | 260161 | District 8 | 1 | $60.00 | $120.00 | 2 | OGLESBY CONSTRUCTION INC | ODOT |
| 04 DEC 2025 | 250530 | MAR | 11 | $275.00 | $121.00 | 5 | SHELLY & SANDS INC | ODOT |
| 27 MAR 2025 | 250158 | HAM | 29 | $385.00 | $385.00 | 2 | JOHN R JURGENSEN COMPANY | ODOT |
| 27 MAR 2025 | 250176 | District 8 | 1 | $1,270.00 | $772.50 | 2 | THE AERO-MARK COMPANY LLC | ODOT |
| 27 FEB 2025 | 250142 | District 6 | 10 | $575.00 | $550.00 | 2 | THE AERO-MARK COMPANY LLC | ODOT |
| 16 JAN 2025 | 240582 | HAM | 3 | $620.00 | $550.00 | 9 | ALAN STONE CO INC | ODOT |
| 25 JUL 2024 | 240379 | OTT | 42 | $400.00 | $357.50 | 2 | GERKEN PAVING INC | ODOT |
| 09 MAY 2024 | 240272 | LOR | 30 | $200.00 | $200.00 | 2 | KOKOSING CONSTRUCTION COMPANY INC | ODOT |
| 09 MAY 2024 | 240284 | TUS | 72 | $360.00 | $355.00 | 2 | SHELLY & SANDS INC | ODOT |
| 21 MAR 2024 | 240196 | District 8 | 1 | $275.00 | $417.50 | 2 | OGLESBY CONSTRUCTION INC | ODOT |
| 08 FEB 2024 | 240090 | HAM | 21 | $550.00 | $550.00 | 3 | EAGLE BRIDGE CO | ODOT |
| 12 OCT 2023 | 230501 | WAR | 8 | $470.00 | $470.00 | 2 | JOHN R JURGENSEN COMPANY | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.