Dotted line, 4" unit price, Ohio
Low bidders on ODOT contracts carried a median of $2.00 per FT for item 644E01500, dotted line, 4", over the 24 months to 12 NOV 2026, across 14 low bids. Half of all 46 bids fell between $1.30 and $3.00.
- Owner
- Ohio DOT
- Item
- 644E01500
- Unit
- FT
- Latest letting
- 13 AUG 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 18 | 18 | $1.55 | 57 | $1.50 |
| 2021 | 17 | 17 | $1.31 | 69 | $1.28 |
| 2022 | 19 | 19 | $2.00 | 56 | $2.00 |
| 2023 | 14 | 14 | $1.95 | 49 | $2.25 |
| 2024 | 15 | 15 | $2.00 | 45 | $2.00 |
| 2025 | 5 | 5 | $1.55 | 20 | $1.43 |
| 2026 | 9 | 9 | $2.00 | 26 | $2.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (FT) | Low bids | Low-bid median |
|---|---|---|
| 78 to 100 | 3 | $4.45 |
| 100 to 149 | 4 | $1.77 |
| 153 to 176 | 3 | $2.00 |
| 228 to 680 | 4 | $1.65 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 13 AUG 2026 | 260364 | KNO | 158 | $2.00 | $2.00 | 4 | COMPLETE GENERAL CONSTRUCTION COMPANY | ODOT |
| 25 JUN 2026 | 260309 | CUY | 680 | $3.00 | $3.00 | 3 | GEAUGA HIGHWAY CO | ODOT |
| 25 JUN 2026 | 260310 | CUY | 153 | $3.00 | $3.00 | 4 | RONYAK PAVING INC | ODOT |
| 07 MAY 2026 | 260232 | CUY | 486 | $1.00 | $1.00 | 3 | PERK COMPANY INC | ODOT |
| 07 MAY 2026 | 260243 | MIA | 85 | $5.00 | $5.00 | 4 | EAGLE BRIDGE CO | ODOT |
| 07 MAY 2026 | 260252 | WAS | 78 | $1.00 | $1.75 | 2 | ALAN STONE CO INC | ODOT |
| 09 APR 2026 | 260168 | ATB | 514 | $2.00 | $2.00 | 1 | UNION INDUSTRIAL CONTRACTORS INC | ODOT |
| 26 MAR 2026 | 260153 | LAW | 106 | $2.00 | $2.00 | 3 | SHELLY COMPANY | ODOT |
| 26 MAR 2026 | 260161 | District 8 | 100 | $0.50 | $1.25 | 2 | OGLESBY CONSTRUCTION INC | ODOT |
| 11 SEP 2025 | 250411 | HAM | 107 | $3.25 | $1.25 | 5 | FORD DEVELOPMENT CORP | ODOT |
| 22 MAY 2025 | 250277 | HAM | 228 | $1.30 | $1.30 | 5 | KT HOLDEN CONSTRUCTION LLC | ODOT |
| 27 MAR 2025 | 250176 | District 8 | 100 | $4.45 | $3.23 | 2 | THE AERO-MARK COMPANY LLC | ODOT |
| 27 FEB 2025 | 250004 | SUM | 149 | $1.55 | $1.55 | 3 | KENMORE CONSTRUCTION CO INC | ODOT |
| 30 JAN 2025 | 250056 | LOR | 176 | $1.00 | $1.00 | 5 | GREAT LAKES DEMOLITION COMPANY | ODOT |
| 26 SEP 2024 | 240416 | CUY | 530 | $2.00 | $1.50 | 5 | J D WILLIAMSON CONSTRUCTION CO INC | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way