Class QC2 concrete, superstructure unit price, Ohio

Low bidders on ODOT contracts carried a median of $2,560.66 per CY for item 511E34410, class qc2 concrete, superstructure, over the 24 months to 12 NOV 2026, across 39 low bids. Half of all 115 bids fell between $1,612.50 and $3,925.00.

Owner
Ohio DOT
Item
511E34410
Unit
CY
Latest letting
01 OCT 2026
$2,560.66Low bidder's median, per CY
$2,500.00Median of all bids, per CY
26Contracts in the window

By year of letting

Class QC2 concrete, superstructure, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20201827$1,600.0086$1,650.00
20211931$2,000.0094$2,000.00
2022912$3,500.0035$3,500.00
20231420$2,642.5058$2,625.00
20241425$2,600.0079$3,088.00
20251217$2,560.6653$2,502.00
20261114$2,629.3935$2,096.06
Class QC2 concrete, superstructure, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Class QC2 concrete, superstructure, ODOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
District 73$1,723.7718$1,930.00
HAM7$6,000.0016$5,215.88
FRA4$1,650.0016$1,775.00
District 84$3,000.009$3,000.00
ROS4$5,491.008$4,407.50
Class QC2 concrete, superstructure, ODOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Class QC2 concrete, superstructure, ODOT: low bidder's median by quantity band
Quantity (CY)Low bidsLow-bid median
1 to 69$3,195.00
10 to 1910$3,400.00
20 to 3610$2,250.00
39 to 29510$1,420.00
Class QC2 concrete, superstructure, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Class QC2 concrete, superstructure
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
01 OCT 2026260435SAN295$375.00$605.003SMITH PAVING & EXCAVATING INCODOT
01 OCT 2026260450SHE20$2,500.00$2,298.034BRUMBAUGH CONSTRUCTION INCODOT
17 SEP 2026260414WAR2$3,000.00$6,785.152AAD CONTRACTING INCODOT
07 MAY 2026260249SCI11$2,758.77$3,575.004BCC OHIO INCODOT
23 APR 2026264009MOT2$3,834.00$3,667.002BCC OHIO INCODOT
26 MAR 2026260124HAM14$6,000.00$6,000.002BARRETT PAVING MATERIALS INCODOT
26 MAR 2026260124HAM14$6,000.00$6,000.002BARRETT PAVING MATERIALS INCODOT
19 FEB 2026260095SAN121$1,290.00$1,225.003ERIE BLACKTOP INCODOT
19 FEB 2026264005MRW1$1,314.00$1,172.002BCC OHIO INCODOT
19 FEB 2026264005MRW39$1,164.00$1,522.002BCC OHIO INCODOT
29 JAN 2026260002HEN36$775.00$1,050.143E S WAGNER - VERNON NAGEL JOINT VENTUREODOT
29 JAN 2026260002HEN61$750.00$750.003E S WAGNER - VERNON NAGEL JOINT VENTUREODOT
15 JAN 2026260009BUT10$3,800.00$3,800.002BARRETT PAVING MATERIALS INCODOT
15 JAN 2026260016HAM1$10,000$10,0001360 CONSTRUCTION COMPANY INCODOT
04 DEC 2025250525HAM3$3,195.00$3,195.006CORROSION RESISTANCE LTDODOT
Latest ODOT contracts carrying Class QC2 concrete, superstructure

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy