Class QC2 concrete with qc/qa, bridge deck, as per unit price, Ohio
Low bidders on ODOT contracts carried a median of $1,120.00 per CY for item 511E34447, class qc2 concrete with qc/qa, bridge deck, as per, over the 24 months to 12 NOV 2026, across 15 low bids. Half of all 40 bids fell between $1,000.00 and $1,231.25.
- Owner
- Ohio DOT
- Item
- 511E34447
- Unit
- CY
- Latest letting
- 29 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 8 | 8 | $760.00 | 47 | $775.00 |
| 2021 | 8 | 13 | $816.55 | 69 | $810.00 |
| 2022 | 5 | 6 | $850.00 | 20 | $850.00 |
| 2023 | 13 | 15 | $1,080.00 | 55 | $1,150.00 |
| 2024 | 6 | 12 | $1,142.50 | 33 | $1,130.00 |
| 2025 | 6 | 9 | $950.00 | 21 | $1,000.00 |
| 2026 | 6 | 6 | $1,200.00 | 19 | $1,155.23 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 158 to 190 | 3 | $1,225.00 |
| 211 to 354 | 4 | $1,225.00 |
| 359 to 470 | 4 | $950.00 |
| 480 to 1,747 | 4 | $1,050.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 29 OCT 2026 | 260475 | WOO | 354 | $1,120.00 | $1,155.23 | 3 | EAGLE BRIDGE CO | ODOT |
| 13 AUG 2026 | 260345 | CUY | 415 | $1,050.00 | $1,050.00 | 4 | GREAT LAKES CONSTRUCTION CO | ODOT |
| 13 AUG 2026 | 260353 | LOR | 211 | $1,450.00 | $1,567.50 | 2 | GREAT LAKES CONSTRUCTION CO | ODOT |
| 09 APR 2026 | 260147 | DEL | 190 | $1,300.00 | $1,600.00 | 3 | COMPLETE GENERAL CONSTRUCTION COMPANY | ODOT |
| 12 MAR 2026 | 260098 | SUM | 176 | $1,225.00 | $1,225.00 | 3 | BLACK HORSE BRIDGE CONSTRUCTION INC | ODOT |
| 05 FEB 2026 | 260003 | MAH | 1,747 | $1,175.00 | $1,037.50 | 4 | SHELLY & SANDS INC | ODOT |
| 09 OCT 2025 | 250467 | MAH | 359 | $900.00 | $940.00 | 4 | A P O'HORO COMPANY | ODOT |
| 25 SEP 2025 | 250428 | BRO | 480 | $900.00 | $900.00 | 1 | COMPLETE GENERAL CONSTRUCTION COMPANY | ODOT |
| 15 MAY 2025 | 250153 | FAI | 158 | $1,120.00 | $1,000.00 | 4 | SHELLY & SANDS INC | ODOT |
| 15 MAY 2025 | 250153 | FAI | 573 | $1,150.00 | $1,050.00 | 4 | SHELLY & SANDS INC | ODOT |
| 10 APR 2025 | 250186 | ATH | 311 | $1,300.00 | $1,300.00 | 1 | KOKOSING CONSTRUCTION COMPANY INC | ODOT |
| 27 MAR 2025 | 250162 | MEG | 486 | $950.00 | $950.00 | 1 | KOKOSING CONSTRUCTION COMPANY INC | ODOT |
| 27 MAR 2025 | 250162 | MEG | 470 | $950.00 | $950.00 | 1 | KOKOSING CONSTRUCTION COMPANY INC | ODOT |
| 27 MAR 2025 | 250162 | MEG | 361 | $950.00 | $950.00 | 1 | KOKOSING CONSTRUCTION COMPANY INC | ODOT |
| 30 JAN 2025 | 250049 | GRE | 329 | $1,150.00 | $1,200.00 | 4 | MILLER BROS CONST INC | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way