Concrete barrier removed, as per plan unit price, Ohio

Low bidders on ODOT contracts carried a median of $39.50 per FT for item 202E30701, concrete barrier removed, as per plan, over the 24 months to 12 NOV 2026, across 14 low bids. Half of all 43 bids fell between $20.77 and $65.00.

Owner
Ohio DOT
Item
202E30701
Unit
FT
Latest letting
29 OCT 2026
$39.50Low bidder's median, per FT
$33.19Median of all bids, per FT
14Contracts in the window

By year of letting

Concrete barrier removed, as per plan, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202066$17.0028$25.50
202166$73.0027$76.00
202299$26.0030$24.25
202344$53.508$76.25
202444$100.008$52.50
202588$39.5029$30.00
202655$30.0012$31.59
Concrete barrier removed, as per plan, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By quantity

Concrete barrier removed, as per plan, ODOT: low bidder's median by quantity band
Quantity (FT)Low bidsLow-bid median
34 to 903$88.00
137.50 to 2164$47.50
231 to 4803$34.00
500 to 18,5404$29.00
Concrete barrier removed, as per plan, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Concrete barrier removed, as per plan
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
29 OCT 2026260467LAW1,935$10.00$12.502ALLARD EXCAVATION LLCODOT
29 OCT 2026268021JEF34$300.00$160.003BUDS INCODOT
30 JUL 2026260327CUY18,540$28.00$28.003RUHLIN COMPANYODOT
26 MAR 2026260146District 12231$70.00$70.001LAKE ERIE CONSTRUCTION COMPANYODOT
29 JAN 2026260001CUY500$30.00$30.003RUHLIN COMPANYODOT
04 DEC 2025250530MAR216$45.00$65.005SHELLY & SANDS INCODOT
13 NOV 2025250527JEF280$18.00$25.003BUDS INCODOT
23 OCT 2025250500LAK480$34.00$34.003J D WILLIAMSON CONSTRUCTION CO INCODOT
25 SEP 2025250445WOO40$17.50$17.507E S WAGNER COMPANYODOT
08 MAY 2025250266District 12202$65.00$65.001LAKE ERIE CONSTRUCTION COMPANYODOT
24 APR 2025250223OTT137.50$16.00$20.003VERNON NAGEL INCODOT
16 JAN 2025250013HAM90$88.00$220.004PRUS CONSTRUCTION COMPANYODOT
16 JAN 2025250022SAN144$50.00$18.003GREAT LAKES DEMOLITION COMPANYODOT
19 DEC 2024240548CUY845$50.00$52.502RUHLIN COMPANYODOT
09 MAY 2024248003District 12834$150.00$90.502CUYAHOGA FENCE LLCODOT
Latest ODOT contracts carrying Concrete barrier removed, as per plan

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.