Traffic island removed unit price, Ohio
Low bidders on ODOT contracts carried a median of $25.00 per SY for item 202E30800, traffic island removed, over the 24 months to 12 NOV 2026, across 13 low bids. Half of all 39 bids fell between $18.75 and $44.00.
- Owner
- Ohio DOT
- Item
- 202E30800
- Unit
- SY
- Latest letting
- 29 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 7 | 7 | $28.00 | 31 | $35.00 |
| 2021 | 4 | 4 | $34.95 | 12 | $48.00 |
| 2022 | 7 | 7 | $18.80 | 26 | $28.75 |
| 2023 | 6 | 6 | $34.00 | 21 | $28.00 |
| 2024 | 8 | 8 | $27.50 | 23 | $28.00 |
| 2025 | 7 | 7 | $25.00 | 23 | $25.10 |
| 2026 | 5 | 5 | $30.00 | 15 | $30.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 15 to 22 | 3 | $75.00 |
| 50 to 94 | 3 | $25.00 |
| 114 to 139 | 3 | $20.00 |
| 176 to 390 | 4 | $13.41 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 29 OCT 2026 | 260399 | CUY | 390 | $15.00 | $22.25 | 4 | TRI-MOR CORP | ODOT |
| 30 JUL 2026 | 260354 | MAH | 311 | $30.00 | $30.00 | 4 | MARUCCI & GAFFNEY EXCAVATING CO | ODOT |
| 07 MAY 2026 | 260232 | CUY | 138 | $50.00 | $50.00 | 3 | PERK COMPANY INC | ODOT |
| 07 MAY 2026 | 260237 | FRA | 21 | $75.00 | $69.00 | 2 | SHELLY & SANDS INC | ODOT |
| 29 JAN 2026 | 260064 | POR | 94 | $25.00 | $25.80 | 2 | KARVO COMPANIES INC | ODOT |
| 23 OCT 2025 | 250488 | BUT | 15 | $110.00 | $115.50 | 2 | JOHN R JURGENSEN COMPANY | ODOT |
| 24 APR 2025 | 250228 | STA | 50 | $28.00 | $26.50 | 2 | WENGER EXCAVATING INC | ODOT |
| 10 APR 2025 | 250191 | District 3 | 22 | $60.00 | $76.15 | 2 | PERK COMPANY INC | ODOT |
| 27 FEB 2025 | 250004 | SUM | 114 | $20.00 | $20.00 | 3 | KENMORE CONSTRUCTION CO INC | ODOT |
| 27 FEB 2025 | 250076 | FRA | 72 | $25.00 | $25.00 | 1 | SHELLY & SANDS INC | ODOT |
| 13 FEB 2025 | 250084 | CUY | 176 | $11.83 | $17.50 | 6 | ANTHONY ALLEGA CEMENT CONTRACTOR INC | ODOT |
| 30 JAN 2025 | 250060 | MOT | 222 | $9.50 | $25.10 | 7 | BARRETT PAVING MATERIALS INC | ODOT |
| 05 DEC 2024 | 240562 | TUS | 139 | $13.00 | $13.00 | 1 | SHELLY & SANDS INC | ODOT |
| 13 JUN 2024 | 240270 | HAM | 79 | $55.00 | $35.31 | 2 | BARRETT PAVING MATERIALS INC | ODOT |
| 23 MAY 2024 | 240306 | LAK | 69 | $55.00 | $31.00 | 4 | RUHLIN COMPANY | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.