Concrete masonry, as per plan unit price, Ohio
Low bidders on ODOT contracts carried a median of $1,800.00 per CY for item 602E20001, concrete masonry, as per plan, over the 24 months to 12 NOV 2026, across 11 low bids. Half of all 47 bids fell between $1,550.00 and $3,000.00.
- Owner
- Ohio DOT
- Item
- 602E20001
- Unit
- CY
- Latest letting
- 29 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 3 | 3 | $1,660.00 | 16 | $1,660.00 |
| 2021 | 10 | 10 | $1,633.87 | 52 | $1,875.00 |
| 2022 | 7 | 7 | $1,300.00 | 20 | $1,500.00 |
| 2023 | 9 | 11 | $1,250.00 | 35 | $1,700.00 |
| 2024 | 5 | 5 | $1,387.78 | 32 | $2,150.00 |
| 2025 | 7 | 7 | $1,800.00 | 28 | $1,800.00 |
| 2026 | 3 | 3 | $1,892.70 | 12 | $3,200.00 |
Bid prices as published, not adjusted for inflation.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 29 OCT 2026 | 260461 | HAM | 0.80 | $1,892.70 | $3,000.00 | 5 | SUNESIS CONSTRUCTION CO | ODOT |
| 01 OCT 2026 | 268019 | NOB | 1 | $3,700.00 | $3,600.00 | 4 | SHELLY & SANDS INC | ODOT |
| 21 MAY 2026 | 260272 | POR | 42 | $1,680.55 | $1,680.55 | 3 | BCC OHIO INC | ODOT |
| 25 SEP 2025 | 250441 | POR | 16 | $1,100.00 | $1,396.00 | 9 | A P O'HORO COMPANY | ODOT |
| 26 JUN 2025 | 250319 | HAM | 3 | $6,021.67 | $6,118.76 | 4 | SUNESIS CONSTRUCTION CO | ODOT |
| 22 MAY 2025 | 250298 | ROS | 20 | $1,800.00 | $1,800.00 | 5 | PARKER CORPORATION | ODOT |
| 24 APR 2025 | 250231 | WAS | 15.60 | $1,800.00 | $2,500.00 | 5 | ALAN STONE CO INC | ODOT |
| 27 MAR 2025 | 250161 | LAK | 8.64 | $2,500.00 | $3,200.00 | 2 | GREAT LAKES CRUSHING LTD | ODOT |
| 27 FEB 2025 | 250076 | FRA | 3 | $2,000.00 | $2,000.00 | 1 | SHELLY & SANDS INC | ODOT |
| 27 FEB 2025 | 250113 | ATB | 26 | $1,200.00 | $1,200.00 | 2 | KARVO COMPANIES INC | ODOT |
| 14 NOV 2024 | 240527 | HOC | 10.40 | $1,700.00 | $1,929.42 | 7 | AXIS CIVIL CONSTRUCTION LLC | ODOT |
| 26 SEP 2024 | 240431 | CLE | 34.20 | $1,387.78 | $1,602.00 | 6 | BCC OHIO INC | ODOT |
| 12 SEP 2024 | 240426 | CLE | 12.39 | $1,190.00 | $2,000.00 | 5 | AXIS CIVIL CONSTRUCTION LLC | ODOT |
| 08 FEB 2024 | 240108 | TUS | 0.11 | $13,636 | $7,500.00 | 13 | DOUBLE B EXCAVATING LLC | ODOT |
| 11 JAN 2024 | 244002 | GEA | 82.70 | $1,300.00 | $1,300.00 | 1 | SHOOK COMPANY LLC | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.