Connection, unfused pull apart unit price, Ohio

Low bidders on ODOT contracts carried a median of $150.00 per EACH for item 625E00460, connection, unfused pull apart, over the 24 months to 12 NOV 2026, across 51 low bids. Half of all 189 bids fell between $125.00 and $180.00.

Owner
Ohio DOT
Item
625E00460
Unit
EACH
Latest letting
12 NOV 2026
$150.00Low bidder's median, per EACH
$150.00Median of all bids, per EACH
50Contracts in the window

By year of letting

Connection, unfused pull apart, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20201112$97.5050$96.50
20212928$100.00123$100.00
20222727$110.0098$111.42
20232928$120.0089$130.00
20242323$140.0087$140.00
20251718$135.7562$134.50
20262929$164.75112$161.50
Connection, unfused pull apart, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Connection, unfused pull apart, ODOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
HAM4$129.1315$125.00
MOT3$120.1814$160.00
CUY4$247.5013$200.00
MAH3$150.0012$150.00
District 33$150.007$148.10
Connection, unfused pull apart, ODOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Connection, unfused pull apart, ODOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 412$148.75
4 to 813$134.00
8 to 1813$164.75
20 to 10713$150.00
Connection, unfused pull apart, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Connection, unfused pull apart
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
12 NOV 2026260515District 312$179.50$149.752PERRAM ELECTRIC INCODOT
12 NOV 2026260516District 7107$143.00$146.504DANBERT ELECTRICAL CORPODOT
12 NOV 2026260524WAR5$182.00$190.007PRUS CONSTRUCTION COMPANYODOT
29 OCT 2026260468MAH8$120.00$133.004SHELLY & SANDS INCODOT
29 OCT 2026260471MOT5$180.00$182.085EAGLE BRIDGE COODOT
01 OCT 2026260445District 632$172.50$129.754PERRAM ELECTRIC INCODOT
27 AUG 2026260391CUY2$300.00$237.506OHIO CONCRETE MAINTENANCE LLCODOT
13 AUG 2026260332STA6$130.00$134.504KENMORE CONSTRUCTION CO INCODOT
13 AUG 2026260364KNO8$170.00$170.004COMPLETE GENERAL CONSTRUCTION COMPANYODOT
13 AUG 2026260368PIK8$163.00$163.009ALLARD EXCAVATION LLCODOT
30 JUL 2026260327CUY98$184.00$155.003RUHLIN COMPANYODOT
30 JUL 2026260341ALL10$172.50$194.005FENSON CONTRACTING LLCODOT
30 JUL 2026268015PRE26$198.96$170.756R B JERGENS CONTRACTORS INCODOT
16 JUL 2026260335District 210$200.00$167.382J RANCK ELECTRIC INCODOT
07 MAY 2026260239HAR10$179.75$190.003EAGLE BRIDGE COODOT
Latest ODOT contracts carrying Connection, unfused pull apart

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy