No. 6 awg 600 volt distribution cable unit price, Ohio
Low bidders on ODOT contracts carried a median of $3.00 per FT for item 625E22990, no. 6 awg 600 volt distribution cable, over the 24 months to 12 NOV 2026, across 14 low bids. Half of all 50 bids fell between $2.51 and $3.33.
- Owner
- Ohio DOT
- Item
- 625E22990
- Unit
- FT
- Latest letting
- 29 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 6 | 6 | $2.43 | 24 | $1.94 |
| 2021 | 9 | 9 | $3.00 | 41 | $3.00 |
| 2022 | 3 | 3 | $2.68 | 13 | $3.03 |
| 2023 | 5 | 5 | $2.35 | 11 | $2.35 |
| 2024 | 3 | 3 | $3.10 | 15 | $3.00 |
| 2025 | 4 | 4 | $2.92 | 18 | $2.50 |
| 2026 | 10 | 10 | $3.12 | 32 | $3.10 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (FT) | Low bids | Low-bid median |
|---|---|---|
| 600 to 1,575 | 3 | $3.00 |
| 2,646 to 3,480 | 4 | $2.62 |
| 3,951 to 7,022 | 3 | $3.35 |
| 7,100 to 34,274 | 4 | $2.70 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 29 OCT 2026 | 260477 | ATB | 2,756 | $3.00 | $2.75 | 3 | KARVO COMPANIES INC | ODOT |
| 15 OCT 2026 | 260483 | District 12 | 600 | $4.00 | $4.00 | 1 | MILLER CABLE COMPANY | ODOT |
| 27 AUG 2026 | 260382 | CUY | 7,022 | $3.25 | $3.25 | 3 | PERK COMPANY INC | ODOT |
| 25 JUN 2026 | 260319 | FRA | 7,100 | $4.60 | $3.77 | 3 | RUHLIN COMPANY | ODOT |
| 11 JUN 2026 | 260293 | CUY | 6,160 | $3.80 | $4.00 | 3 | RUHLIN COMPANY | ODOT |
| 07 MAY 2026 | 260243 | MIA | 1,575 | $1.57 | $3.50 | 4 | EAGLE BRIDGE CO | ODOT |
| 07 MAY 2026 | 260251 | MOT | 3,951 | $3.35 | $3.35 | 2 | JOHN R JURGENSEN COMPANY | ODOT |
| 29 JAN 2026 | 260055 | LAK | 34,274 | $2.55 | $2.88 | 2 | PERRAM ELECTRIC INC | ODOT |
| 29 JAN 2026 | 260059 | MER | 2,646 | $2.00 | $3.25 | 4 | JUTTE EXCAVATING INC | ODOT |
| 15 JAN 2026 | 268000 | TRU | 3,480 | $2.25 | $2.64 | 7 | SHELLY & SANDS INC | ODOT |
| 18 DEC 2025 | 250592 | MIA | 10,209 | $1.08 | $1.25 | 7 | EAGLE BRIDGE CO | ODOT |
| 09 OCT 2025 | 250404 | HAM | 2,655 | $3.20 | $3.20 | 3 | GREAT LAKES CONSTRUCTION CO | ODOT |
| 15 MAY 2025 | 250153 | FAI | 1,134 | $3.00 | $2.49 | 4 | SHELLY & SANDS INC | ODOT |
| 16 JAN 2025 | 250013 | HAM | 18,390 | $2.85 | $2.55 | 4 | PRUS CONSTRUCTION COMPANY | ODOT |
| 12 SEP 2024 | 240420 | MEG | 12,285 | $3.10 | $3.00 | 7 | AXIS CIVIL CONSTRUCTION LLC | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.