Epoxy coated reinforcing steel, as per plan unit price, Ohio
Low bidders on ODOT contracts carried a median of $2.00 per LB for item 509E10001, epoxy coated reinforcing steel, as per plan, from 13 FEB 2020 to 14 SEP 2023, across 103 low bids. Half of all 406 bids fell between $1.35 and $2.65.
- Owner
- Ohio DOT
- Item
- 509E10001
- Unit
- LB
- Latest letting
- 14 SEP 2023
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 21 | 36 | $1.88 | 153 | $1.64 |
| 2021 | 22 | 31 | $1.35 | 136 | $1.49 |
| 2022 | 7 | 11 | $5.25 | 35 | $5.25 |
| 2023 | 10 | 25 | $2.60 | 82 | $2.65 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| SUM | 14 | $2.54 | 49 | $2.65 |
| HUR | 12 | $2.00 | 48 | $2.05 |
| STA | 4 | $1.43 | 25 | $1.50 |
| FRA | 6 | $1.05 | 23 | $1.10 |
| MOT | 4 | $1.25 | 20 | $1.25 |
| POR | 4 | $10.00 | 16 | $10.00 |
| LIC | 4 | $2.04 | 13 | $2.25 |
| RIC | 4 | $4.47 | 12 | $4.51 |
| MUS | 4 | $1.27 | 12 | $1.33 |
| WAR | 3 | $1.65 | 12 | $1.95 |
| MAH | 5 | $6.25 | 11 | $6.25 |
| LUC | 3 | $1.65 | 11 | $1.65 |
Countys with at least three low bids, over all lettings.
By quantity
| Quantity (LB) | Low bids | Low-bid median |
|---|---|---|
| 100 to 909 | 25 | $2.00 |
| 974 to 8,444 | 26 | $3.50 |
| 9,010 to 76,825 | 26 | $1.45 |
| 76,935 to 1,681,231 | 26 | $1.33 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 14 SEP 2023 | 230443 | BEL | 4,031 | $3.50 | $3.25 | 4 | SHELLY & SANDS INC | ODOT |
| 31 AUG 2023 | 230437 | SUM | 32,875 | $2.48 | $2.65 | 5 | KENMORE CONSTRUCTION CO INC | ODOT |
| 31 AUG 2023 | 230437 | SUM | 33,459 | $2.48 | $2.60 | 5 | KENMORE CONSTRUCTION CO INC | ODOT |
| 31 AUG 2023 | 230437 | SUM | 32,668 | $2.45 | $2.65 | 5 | KENMORE CONSTRUCTION CO INC | ODOT |
| 31 AUG 2023 | 230437 | SUM | 33,156 | $2.45 | $2.65 | 5 | KENMORE CONSTRUCTION CO INC | ODOT |
| 31 AUG 2023 | 230437 | SUM | 33,438 | $2.60 | $2.65 | 5 | KENMORE CONSTRUCTION CO INC | ODOT |
| 31 AUG 2023 | 230437 | SUM | 37,285 | $2.46 | $2.65 | 5 | KENMORE CONSTRUCTION CO INC | ODOT |
| 27 JUL 2023 | 230403 | MAH | 909 | $6.25 | $6.25 | 2 | SHELLY & SANDS INC | ODOT |
| 27 JUL 2023 | 230403 | MAH | 2,468 | $8.75 | $8.75 | 2 | SHELLY & SANDS INC | ODOT |
| 27 JUL 2023 | 230403 | MAH | 986 | $8.75 | $8.75 | 2 | SHELLY & SANDS INC | ODOT |
| 27 JUL 2023 | 230403 | MAH | 986 | $3.50 | $3.50 | 2 | SHELLY & SANDS INC | ODOT |
| 25 MAY 2023 | 230334 | SUM | 974 | $5.02 | $5.01 | 2 | KENMORE CONSTRUCTION CO INC | ODOT |
| 25 MAY 2023 | 230334 | SUM | 1,005 | $5.02 | $5.01 | 2 | KENMORE CONSTRUCTION CO INC | ODOT |
| 25 MAY 2023 | 230334 | SUM | 1,446 | $5.02 | $5.01 | 2 | KENMORE CONSTRUCTION CO INC | ODOT |
| 25 MAY 2023 | 230334 | SUM | 1,350 | $5.02 | $5.01 | 2 | KENMORE CONSTRUCTION CO INC | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.