Steel points or shoes unit price, Ohio
Low bidders on ODOT contracts carried a median of $190.00 per EACH for item 507E93300, steel points or shoes, over the 24 months to 12 NOV 2026, across 22 low bids. Half of all 86 bids fell between $141.25 and $358.75.
- Owner
- Ohio DOT
- Item
- 507E93300
- Unit
- EACH
- Latest letting
- 29 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 7 | 8 | $100.00 | 42 | $115.12 |
| 2021 | 8 | 10 | $100.00 | 60 | $125.00 |
| 2022 | 5 | 8 | $140.00 | 29 | $145.00 |
| 2023 | 4 | 7 | $175.00 | 22 | $347.50 |
| 2024 | 3 | 3 | $140.00 | 26 | $149.00 |
| 2025 | 9 | 13 | $200.00 | 38 | $160.00 |
| 2026 | 8 | 8 | $315.00 | 36 | $265.76 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| FRA | 5 | $350.00 | 14 | $352.50 |
| UNI | 3 | $145.00 | 12 | $140.00 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 7 to 18 | 5 | $145.00 |
| 18 to 30 | 6 | $165.00 |
| 34 to 59 | 5 | $350.00 |
| 72 to 211 | 6 | $345.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 29 OCT 2026 | 260469 | MOT | 36 | $450.00 | $462.50 | 6 | DOUBLE Z CONSTRUCTION COMPANY | ODOT |
| 29 OCT 2026 | 260471 | MOT | 96 | $550.00 | $515.00 | 5 | EAGLE BRIDGE CO | ODOT |
| 13 AUG 2026 | 260363 | HAS | 34 | $165.00 | $173.00 | 5 | J D WILLIAMSON CONSTRUCTION CO INC | ODOT |
| 25 JUN 2026 | 260307 | COS | 30 | $145.00 | $142.50 | 4 | COMPLETE GENERAL CONSTRUCTION COMPANY | ODOT |
| 07 MAY 2026 | 260212 | PRE | 28 | $500.00 | $500.00 | 5 | BRUMBAUGH CONSTRUCTION INC | ODOT |
| 23 APR 2026 | 260216 | VAN | 20 | $180.00 | $165.00 | 2 | VERNON NAGEL INC | ODOT |
| 12 MAR 2026 | 260130 | NOB | 10 | $175.00 | $150.00 | 5 | J & J BRIDGE COMPANY INC | ODOT |
| 19 FEB 2026 | 260078 | CLI | 14 | $600.00 | $240.76 | 4 | EAGLE BRIDGE CO | ODOT |
| 25 SEP 2025 | 250428 | BRO | 74 | $135.00 | $135.00 | 1 | COMPLETE GENERAL CONSTRUCTION COMPANY | ODOT |
| 11 SEP 2025 | 250399 | WOO | 20 | $115.00 | $130.75 | 3 | VERNON NAGEL INC | ODOT |
| 24 APR 2025 | 250212 | ATH | 22 | $200.00 | $200.00 | 1 | KOKOSING CONSTRUCTION COMPANY INC | ODOT |
| 17 APR 2025 | 250151 | FRA | 59 | $350.00 | $352.50 | 4 | COMPLETE GENERAL CONSTRUCTION COMPANY | ODOT |
| 17 APR 2025 | 250151 | FRA | 59 | $350.00 | $357.50 | 4 | COMPLETE GENERAL CONSTRUCTION COMPANY | ODOT |
| 17 APR 2025 | 250151 | FRA | 72 | $350.00 | $362.50 | 4 | COMPLETE GENERAL CONSTRUCTION COMPANY | ODOT |
| 27 MAR 2025 | 250150 | UNI | 18 | $145.00 | $138.50 | 4 | MILLER BROS CONST INC | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.