Full depth pavement removal and rigid replacement, unit price, Ohio
Low bidders on ODOT contracts carried a median of $192.50 per SY for item 255E10011, full depth pavement removal and rigid replacement,, from 23 JAN 2020 to 22 AUG 2024, across 54 low bids. Half of all 184 bids fell between $127.25 and $231.25.
- Owner
- Ohio DOT
- Item
- 255E10011
- Unit
- SY
- Latest letting
- 22 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 12 | 12 | $179.50 | 54 | $139.00 |
| 2021 | 10 | 10 | $187.50 | 34 | $140.00 |
| 2022 | 10 | 13 | $165.00 | 36 | $175.00 |
| 2023 | 9 | 11 | $190.00 | 33 | $224.00 |
| 2024 | 7 | 8 | $317.50 | 27 | $200.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| CUY | 22 | $122.50 | 99 | $135.00 |
| JEF | 9 | $213.00 | 22 | $222.00 |
| BEL | 6 | $277.20 | 18 | $311.00 |
| COL | 3 | $230.00 | 10 | $242.00 |
Countys with at least three low bids, over all lettings.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 72 to 425 | 13 | $235.00 |
| 500 to 1,500 | 14 | $218.50 |
| 1,575 to 2,500 | 13 | $164.00 |
| 2,882 to 21,680 | 14 | $136.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 22 AUG 2024 | 240402 | GRE | 1,575 | $370.00 | $378.98 | 4 | EAGLE BRIDGE CO | ODOT |
| 09 MAY 2024 | 240274 | MEG | 8,896 | $138.50 | $185.00 | 6 | SHELLY COMPANY | ODOT |
| 04 APR 2024 | 240169 | CUY | 2,300 | $160.00 | $160.00 | 3 | SHELLY COMPANY | ODOT |
| 21 MAR 2024 | 240185 | MRW | 275 | $265.00 | $232.50 | 2 | SHELLY & SANDS INC | ODOT |
| 22 FEB 2024 | 240126 | BEL | 500 | $425.00 | $487.50 | 2 | SHELLY & SANDS INC | ODOT |
| 22 FEB 2024 | 240131 | CUY | 1,700 | $180.00 | $182.50 | 6 | C A AGRESTA CONSTRUCTION CO | ODOT |
| 25 JAN 2024 | 240055 | JEF | 425 | $380.00 | $402.50 | 2 | SHELLY & SANDS INC | ODOT |
| 25 JAN 2024 | 240055 | JEF | 600 | $408.00 | $409.00 | 2 | SHELLY & SANDS INC | ODOT |
| 14 DEC 2023 | 230561 | BEL | 1,121 | $350.00 | $400.00 | 2 | NLS PAVING, INC | ODOT |
| 14 DEC 2023 | 230588 | ALL | 11,078 | $149.00 | $176.00 | 4 | SMITH PAVING & EXCAVATING INC | ODOT |
| 28 SEP 2023 | 230473 | MAR | 938 | $99.50 | $107.25 | 2 | KOKOSING CONSTRUCTION COMPANY INC | ODOT |
| 11 MAY 2023 | 230286 | CUY | 1,488 | $225.00 | $190.00 | 3 | PERK COMPANY INC | ODOT |
| 30 MAR 2023 | 230177 | CUY | 78 | $180.00 | $180.00 | 4 | MILLER CABLE COMPANY | ODOT |
| 09 MAR 2023 | 230141 | CUY | 2,500 | $122.00 | $136.00 | 2 | KARVO COMPANIES INC | ODOT |
| 23 FEB 2023 | 230112 | ATH | 3,768 | $190.00 | $190.00 | 1 | SHELLY & SANDS INC | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.