Full depth pavement removal and rigid replacement, unit price, Ohio

Low bidders on ODOT contracts carried a median of $227.00 per SY for item 255E10161, full depth pavement removal and rigid replacement,, from 23 JAN 2020 to 18 JUL 2024, across 56 low bids. Half of all 168 bids fell between $150.00 and $300.16.

Owner
Ohio DOT
Item
255E10161
Unit
SY
Latest letting
18 JUL 2024
$227.00Low bidder's median, per SY
$199.00Median of all bids, per SY
49Contracts in the window

By year of letting

Full depth pavement removal and rigid replacement,, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202077$200.0023$172.00
20211215$150.0051$150.00
20221112$251.5030$225.00
2023911$260.0027$279.00
20241011$340.0037$325.00
Full depth pavement removal and rigid replacement,, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Full depth pavement removal and rigid replacement,, ODOT: unit prices by county, all lettings
CountyLow bidsLow-bid medianAll bidsMedian, all bids
CUY10$149.0053$170.00
FRA11$255.0021$290.00
LOR5$225.0018$206.00
MED3$125.009$150.00
RIC3$180.006$186.00
Full depth pavement removal and rigid replacement,, ODOT: unit prices by county, all lettings

Countys with at least three low bids, over all lettings.

By quantity

Full depth pavement removal and rigid replacement,, ODOT: low bidder's median by quantity band
Quantity (SY)Low bidsLow-bid median
11 to 24014$330.00
240 to 67814$230.00
728 to 2,00014$215.00
2,309 to 16,37014$168.50
Full depth pavement removal and rigid replacement,, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Full depth pavement removal and rigid replacement,
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
18 JUL 2024240266FRA277$580.00$552.502COMPLETE GENERAL CONSTRUCTION COMPANYODOT
11 JUL 2024240360BRO128$600.00$540.003BROWN COUNTY ASPHALT INCODOT
27 JUN 2024240348LAK276$365.00$365.003SHELLY COMPANYODOT
27 JUN 2024240348LAK14$340.00$340.003SHELLY COMPANYODOT
27 JUN 2024240355DEL634$390.00$390.003SHELLY & SANDS INCODOT
18 APR 2024240245ROS240$325.00$379.002SHELLY & SANDS INCODOT
04 APR 2024240208ERI1,099$145.00$140.502ERIE BLACKTOP INCODOT
22 FEB 2024240152UNI11,575$229.00$275.003SHELLY & SANDS INCODOT
08 FEB 2024240104ROS160$572.00$911.002SHELLY COMPANYODOT
08 FEB 2024240112WAY5,694$135.00$167.007SMITH PAVING & EXCAVATING INCODOT
25 JAN 2024230593CUY1,500$195.00$185.007COLE BURTON CONTRACTORS, LLCODOT
14 DEC 2023230592CUY100$340.00$256.004SHELLY COMPANYODOT
14 DEC 2023230592CUY11$216.00$300.504SHELLY COMPANYODOT
09 NOV 2023230535CUY678$200.00$200.004PERK COMPANY INCODOT
28 SEP 2023230477PIK1,000$550.00$456.502SHELLY & SANDS INCODOT
Latest ODOT contracts carrying Full depth pavement removal and rigid replacement,

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.