Geotextile fabric, as per plan unit price, Ohio
Low bidders on ODOT contracts carried a median of $2.66 per SY for item 204E50001, geotextile fabric, as per plan, over the 24 months to 12 NOV 2026, across 8 low bids. Half of all 31 bids fell between $2.00 and $4.76.
- Owner
- Ohio DOT
- Item
- 204E50001
- Unit
- SY
- Latest letting
- 12 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 6 | 6 | $4.00 | 45 | $4.00 |
| 2021 | 8 | 8 | $2.85 | 40 | $3.24 |
| 2022 | 10 | 10 | $2.74 | 34 | $2.87 |
| 2023 | 7 | 8 | $4.50 | 21 | $3.37 |
| 2024 | 1 | 2 | $1.00 | 6 | $4.00 |
| 2025 | 5 | 5 | $2.50 | 22 | $2.25 |
| 2026 | 3 | 3 | $5.00 | 9 | $4.25 |
Bid prices as published, not adjusted for inflation.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 12 NOV 2026 | 260492 | CLA | 21 | $10.00 | $19.00 | 3 | FILLMORE CONSTRUCTION | ODOT |
| 26 FEB 2026 | 260041 | LIC | 2,784 | $2.75 | $2.88 | 2 | KOKOSING CONSTRUCTION COMPANY INC | ODOT |
| 19 FEB 2026 | 260096 | SUM | 1,670 | $5.00 | $3.62 | 4 | KENMORE CONSTRUCTION CO INC | ODOT |
| 18 DEC 2025 | 250584 | District 5 | 2,798 | $2.50 | $2.25 | 2 | LAKE ERIE CONSTRUCTION COMPANY | ODOT |
| 18 DEC 2025 | 254034 | MOE | 936 | $2.56 | $2.78 | 4 | S.T.A.R.T., LLC | ODOT |
| 04 DEC 2025 | 250559 | HOC | 4,467 | $3.00 | $1.50 | 5 | COMPLETE GENERAL CONSTRUCTION COMPANY | ODOT |
| 24 APR 2025 | 250215 | District 5 | 1,388 | $2.00 | $2.00 | 3 | M P DORY CO | ODOT |
| 10 APR 2025 | 250188 | BEL | 1,725 | $2.00 | $3.67 | 8 | OHIO-WEST VIRGINIA EXCAVATING CO | ODOT |
| 08 FEB 2024 | 240090 | HAM | 583 | $1.00 | $4.00 | 3 | EAGLE BRIDGE CO | ODOT |
| 08 FEB 2024 | 240090 | HAM | 583 | $1.00 | $4.00 | 3 | EAGLE BRIDGE CO | ODOT |
| 09 NOV 2023 | 230534 | CLI | 259 | $3.00 | $3.98 | 5 | AXIS CIVIL CONSTRUCTION LLC | ODOT |
| 12 OCT 2023 | 230467 | HAM | 3,572 | $2.64 | $3.37 | 3 | SUNESIS CONSTRUCTION CO | ODOT |
| 14 SEP 2023 | 230446 | District 5 | 7,801 | $1.50 | $1.75 | 2 | M P DORY CO | ODOT |
| 08 JUN 2023 | 230360 | HAM | 134 | $15.00 | $14.25 | 2 | BARRETT PAVING MATERIALS INC | ODOT |
| 23 FEB 2023 | 230127 | MOT | 683 | $6.00 | $6.00 | 1 | COMPLETE GENERAL CONSTRUCTION COMPANY | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.