Granular material, type c unit price, Ohio

Low bidders on ODOT contracts carried a median of $70.00 per CY for item 204E30020, granular material, type c, over the 24 months to 12 NOV 2026, across 50 low bids. Half of all 206 bids fell between $60.50 and $96.50.

Owner
Ohio DOT
Item
204E30020
Unit
CY
Latest letting
12 NOV 2026
$70.00Low bidder's median, per CY
$75.62Median of all bids, per CY
48Contracts in the window

By year of letting

Granular material, type c, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20201919$50.0072$55.00
20212728$58.50146$60.00
20222121$65.0065$64.00
20232626$67.5088$70.14
20242524$59.8289$65.00
20252425$70.00106$72.00
20262223$75.0090$84.50
Granular material, type c, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Granular material, type c, ODOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
HAM7$75.0028$90.00
MOT3$62.7220$71.50
WAR4$72.7018$89.70
ROS4$68.0016$76.50
HEN3$54.508$56.50
Granular material, type c, ODOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Granular material, type c, ODOT: low bidder's median by quantity band
Quantity (CY)Low bidsLow-bid median
15 to 16612$80.00
200 to 59313$70.00
631 to 1,82412$71.20
2,018 to 13,74513$58.00
Granular material, type c, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Granular material, type c
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
12 NOV 2026260521GUE254$100.00$109.868SHELLY & SANDS INCODOT
12 NOV 2026260524WAR166$75.00$85.007PRUS CONSTRUCTION COMPANYODOT
29 OCT 2026260471MOT35$75.00$80.005EAGLE BRIDGE COODOT
15 OCT 2026260484GAL593$89.00$95.003ALLARD EXCAVATION LLCODOT
01 OCT 2026260427LAW137$89.00$120.004ALLARD EXCAVATION LLCODOT
01 OCT 2026260430MOT50$62.72$74.988R B JERGENS CONTRACTORS INCODOT
01 OCT 2026260449HEN562$63.00$60.502E S WAGNER - VERNON NAGEL JOINT VENTUREODOT
27 AUG 2026260358WOO154$46.50$71.814EBONY CONSTRUCTION COODOT
13 AUG 2026260332STA803$65.00$92.504KENMORE CONSTRUCTION CO INCODOT
07 MAY 2026260238HAM723$100.60$98.003SUNESIS CONSTRUCTION COODOT
07 MAY 2026260248SAN15$70.00$74.003GREAT LAKES DEMOLITION COMPANYODOT
23 APR 2026260213ROS104$66.00$89.006FILLMORE CONSTRUCTIONODOT
23 APR 2026260216VAN398$60.50$55.252VERNON NAGEL INCODOT
23 APR 2026260216VAN1,097$60.50$62.752VERNON NAGEL INCODOT
09 APR 2026260170CLE631$104.06$90.003JOHN R JURGENSEN COMPANYODOT
Latest ODOT contracts carrying Granular material, type c

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy