Guardrail removed unit price, Ohio

Low bidders on ODOT contracts carried a median of $3.00 per FT for item 202E38000, guardrail removed, over the 24 months to 12 NOV 2026, across 408 low bids. Half of all 1,476 bids fell between $2.10 and $6.00.

Owner
Ohio DOT
Item
202E38000
Unit
FT
Latest letting
12 NOV 2026
$3.00Low bidder's median, per FT
$3.00Median of all bids, per FT
401Contracts in the window

By year of letting

Guardrail removed, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
2020230251$2.001,263$2.30
2021215227$2.001,104$2.10
2022206219$2.50821$2.50
2023192194$2.50658$2.80
2024173173$2.80629$3.00
2025190194$3.00719$3.00
2026186189$3.00658$3.01
Guardrail removed, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Guardrail removed, ODOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
CUY22$3.0076$3.24
HAM20$5.2564$5.75
BEL11$5.0038$5.62
MOT8$5.0037$6.00
ROS8$9.5037$4.60
FRA13$2.8036$2.62
LAW10$4.2534$5.00
SUM8$2.4533$2.50
POR8$2.4033$2.40
LIC6$2.0031$3.50
GEA8$3.0030$3.00
RIC8$2.0030$2.66
Guardrail removed, ODOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Guardrail removed, ODOT: low bidder's median by quantity band
Quantity (FT)Low bidsLow-bid median
8 to 213102$5.00
214 to 462.50102$3.00
463 to 1,476.50102$2.40
1,477 to 30,932102$2.00
Guardrail removed, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Guardrail removed
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
12 NOV 2026260459FUL412.50$3.00$2.005TOLEDO CAISSON CORPORATIONODOT
12 NOV 2026260489ASD8,635.25$2.00$2.002SHELLY & SANDS INCODOT
12 NOV 2026260501GEA512.50$2.00$2.504J D WILLIAMSON CONSTRUCTION CO INCODOT
12 NOV 2026260502HAM138$7.00$5.004ALAN STONE CO INCODOT
12 NOV 2026260506LUC725$2.60$2.302SHELLY COMPANYODOT
12 NOV 2026260508RIC450$2.00$2.528GREAT LAKES DEMOLITION COMPANYODOT
12 NOV 2026260509SCI62.50$16.00$6.005AXIS CIVIL CONSTRUCTION LLCODOT
12 NOV 2026260512TRU950$5.00$5.005A P O'HORO COMPANYODOT
12 NOV 2026260513BEL1,124$2.80$2.801SHELLY & SANDS INCODOT
12 NOV 2026260521GUE253$5.00$3.758SHELLY & SANDS INCODOT
12 NOV 2026260524WAR120$3.50$10.007PRUS CONSTRUCTION COMPANYODOT
12 NOV 2026264030CUY403$6.00$8.794J D WILLIAMSON CONSTRUCTION CO INCODOT
29 OCT 2026260399CUY2,287$2.00$2.004TRI-MOR CORPODOT
29 OCT 2026260417LOR144$5.00$5.007CORROSION RESISTANCE LTDODOT
29 OCT 2026260454ADA788$1.00$4.505D G M INCODOT
Latest ODOT contracts carrying Guardrail removed

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy