Pipe removed, over 24" diameter unit price, Ohio

Low bidders on ODOT contracts carried a median of $50.00 per FT for item 202E35200, pipe removed, over 24" diameter, over the 24 months to 12 NOV 2026, across 110 low bids. Half of all 414 bids fell between $33.33 and $100.00.

Owner
Ohio DOT
Item
202E35200
Unit
FT
Latest letting
12 NOV 2026
$50.00Low bidder's median, per FT
$52.40Median of all bids, per FT
111Contracts in the window

By year of letting

Pipe removed, over 24" diameter, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202444$71.0021$75.00
20255958$47.40238$50.00
20264848$50.00155$54.00
Pipe removed, over 24" diameter, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Pipe removed, over 24" diameter, ODOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
FRA6$40.0020$40.00
WAY6$79.0019$112.00
HAM4$58.9217$40.50
DEL3$80.0015$80.00
RIC3$45.0014$50.00
LAW4$69.1713$40.00
CUY3$39.3012$39.15
GEA3$65.0011$40.00
GAL4$50.0011$75.00
ROS3$40.0011$30.00
ALL3$50.009$85.00
MEG3$70.008$52.50
Pipe removed, over 24" diameter, ODOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Pipe removed, over 24" diameter, ODOT: low bidder's median by quantity band
Quantity (FT)Low bidsLow-bid median
4 to 3027$55.00
31 to 7028$54.89
70 to 14627$40.00
148 to 3,15328$40.00
Pipe removed, over 24" diameter, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Pipe removed, over 24" diameter
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
12 NOV 2026260492CLA48$100.00$37.003FILLMORE CONSTRUCTIONODOT
29 OCT 2026260399CUY1,018$33.00$30.504TRI-MOR CORPODOT
29 OCT 2026260461HAM107$33.52$33.525SUNESIS CONSTRUCTION COODOT
29 OCT 2026260468MAH148$113.00$81.504SHELLY & SANDS INCODOT
08 OCT 2026260398HAM1,450$114.54$114.541JOHN R JURGENSEN COMPANYODOT
01 OCT 2026260427LAW31$104.00$47.504ALLARD EXCAVATION LLCODOT
01 OCT 2026260429MED12$65.00$57.506FECHKO EXCAVATING LLCODOT
01 OCT 2026264025CLI100$71.94$60.005KT HOLDEN CONSTRUCTION LLCODOT
27 AUG 2026264020CAR67$100.00$118.192BOG CONSTRUCTION INCODOT
27 AUG 2026264021FRA305$40.00$35.002AXIS CIVIL CONSTRUCTION LLCODOT
13 AUG 2026260332STA430$25.00$48.254KENMORE CONSTRUCTION CO INCODOT
13 AUG 2026260361GAL35$50.00$111.004AXIS CIVIL CONSTRUCTION LLCODOT
30 JUL 2026268015PRE250$52.23$56.116R B JERGENS CONTRACTORS INCODOT
16 JUL 2026264018MRG71$100.00$109.004ALAN STONE CO INCODOT
25 JUN 2026268014POR151$30.55$40.003ECLIPSE CO LLCODOT
Latest ODOT contracts carrying Pipe removed, over 24" diameter

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy