Increased barrier delineation unit price, Ohio

Low bidders on ODOT contracts carried a median of $1.98 per FT for item 614E11630, increased barrier delineation, over the 24 months to 12 NOV 2026, across 94 low bids. Half of all 300 bids fell between $1.50 and $2.73.

Owner
Ohio DOT
Item
614E11630
Unit
FT
Latest letting
12 NOV 2026
$1.98Low bidder's median, per FT
$2.00Median of all bids, per FT
94Contracts in the window

By year of letting

Increased barrier delineation, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20204342$2.12225$2.35
20214950$2.00240$2.09
20225353$2.25194$3.00
20234848$2.00143$2.93
20244444$2.75152$2.35
20253535$2.00105$2.32
20265252$1.83172$1.90
Increased barrier delineation, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Increased barrier delineation, ODOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
CUY10$2.4231$2.19
HAM7$2.3524$2.13
District 14$1.9318$2.00
GEA4$4.1216$2.38
FRA6$1.3815$1.00
SCI3$1.9212$1.96
LAW4$1.5012$1.77
SAN3$2.009$2.00
ATH3$0.909$2.00
SUM3$2.918$3.25
MOT3$3.048$2.29
Increased barrier delineation, ODOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Increased barrier delineation, ODOT: low bidder's median by quantity band
Quantity (FT)Low bidsLow-bid median
50 to 32023$2.50
320 to 96124$1.99
1,000 to 2,95023$1.75
3,140 to 46,46624$1.10
Increased barrier delineation, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Increased barrier delineation
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
12 NOV 2026260497District 1400$5.06$2.124BCC OHIO INCODOT
12 NOV 2026260502HAM100$2.00$1.904ALAN STONE CO INCODOT
12 NOV 2026260509SCI320$2.00$2.205AXIS CIVIL CONSTRUCTION LLCODOT
29 OCT 2026260399CUY505$4.00$3.004TRI-MOR CORPODOT
29 OCT 2026260454ADA1,670$1.75$1.755D G M INCODOT
29 OCT 2026260461HAM600$1.79$1.805SUNESIS CONSTRUCTION COODOT
29 OCT 2026260467LAW55$2.00$2.002ALLARD EXCAVATION LLCODOT
29 OCT 2026268021JEF3,140$1.20$2.003BUDS INCODOT
08 OCT 2026260398HAM8,000$3.96$3.961JOHN R JURGENSEN COMPANYODOT
01 OCT 2026260405DEL900$0.50$1.703SHELLY & SANDS INCODOT
01 OCT 2026260425HAM560$1.86$1.865SUNESIS CONSTRUCTION COODOT
01 OCT 2026260427LAW1,600$1.00$1.504ALLARD EXCAVATION LLCODOT
01 OCT 2026260435SAN280$6.00$2.103SMITH PAVING & EXCAVATING INCODOT
17 SEP 2026264023BEL610$1.15$1.322J & J BRIDGE COMPANY INCODOT
27 AUG 2026260358WOO240$3.40$3.004EBONY CONSTRUCTION COODOT
Latest ODOT contracts carrying Increased barrier delineation

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy