Special - work zone traffic signal unit price, Ohio

Low bidders on ODOT contracts carried a median of $20,000 per EACH for item 614E11300, special - work zone traffic signal, over the 24 months to 12 NOV 2026, across 39 low bids. Half of all 119 bids fell between $11,472 and $45,000.

Owner
Ohio DOT
Item
614E11300
Unit
EACH
Latest letting
12 NOV 2026
$20,000Low bidder's median, per EACH
$22,500Median of all bids, per EACH
39Contracts in the window

By year of letting

Special - work zone traffic signal, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20201010$24,95153$29,700
20212322$19,782120$16,620
20221313$12,50053$10,000
20231313$22,36942$21,185
20241717$15,00057$18,000
20251414$19,53841$25,000
20262020$25,52859$21,056
Special - work zone traffic signal, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Special - work zone traffic signal, ODOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
GEA5$33,50020$43,500
FRA4$33,25011$22,980
MAH3$15,0009$15,000
Special - work zone traffic signal, ODOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Special - work zone traffic signal, ODOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 19$33,500
1 to 210$31,750
2 to 310$18,528
4 to 2410$6,224.50
Special - work zone traffic signal, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Special - work zone traffic signal
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
12 NOV 2026260501GEA4$12,000$12,5004J D WILLIAMSON CONSTRUCTION CO INCODOT
29 OCT 2026260399CUY3$30,700$33,4314TRI-MOR CORPODOT
29 OCT 2026260469MOT2$15,000$18,7256DOUBLE Z CONSTRUCTION COMPANYODOT
08 OCT 2026260398HAM3$21,056$21,0561JOHN R JURGENSEN COMPANYODOT
01 OCT 2026260405DEL2$49,500$49,5003SHELLY & SANDS INCODOT
01 OCT 2026260449HEN2$8,434.79$14,5672E S WAGNER - VERNON NAGEL JOINT VENTUREODOT
13 AUG 2026260332STA4$3,000.00$3,000.004KENMORE CONSTRUCTION CO INCODOT
13 AUG 2026260364KNO1$30,000$30,0004COMPLETE GENERAL CONSTRUCTION COMPANYODOT
30 JUL 2026260354MAH3$16,000$15,5004MARUCCI & GAFFNEY EXCAVATING COODOT
30 JUL 2026260355MEG2$2,800.00$2,800.001SHELLY COMPANYODOT
07 MAY 2026260167ERI3$65,000$49,8053GREAT LAKES DEMOLITION COMPANYODOT
07 MAY 2026260237FRA1$35,000$37,5002SHELLY & SANDS INCODOT
23 APR 2026260221FRA1$31,500$28,2502COMPLETE GENERAL CONSTRUCTION COMPANYODOT
09 APR 2026260171COL19$6,199.00$4,599.502SHELLY & SANDS INCODOT
09 APR 2026260185WAS2$32,000$22,5643SHELLY & SANDS INCODOT
Latest ODOT contracts carrying Special - work zone traffic signal

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy