Low strength mortar backfill unit price, Ohio

Low bidders on ODOT contracts carried a median of $210.00 per CY for item 613E41200, low strength mortar backfill, over the 24 months to 12 NOV 2026, across 43 low bids. Half of all 170 bids fell between $171.25 and $271.25.

Owner
Ohio DOT
Item
613E41200
Unit
CY
Latest letting
01 OCT 2026
$210.00Low bidder's median, per CY
$203.47Median of all bids, per CY
38Contracts in the window

By year of letting

Low strength mortar backfill, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20202122$135.00108$150.00
20212223$125.00122$145.50
20222831$139.73153$150.00
20232330$212.50104$232.50
20241919$165.0075$180.00
20252124$208.0097$210.00
20261517$250.0063$215.00
Low strength mortar backfill, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Low strength mortar backfill, ODOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
HAS4$255.0011$248.50
FRA4$197.506$197.50
Low strength mortar backfill, ODOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Low strength mortar backfill, ODOT: low bidder's median by quantity band
Quantity (CY)Low bidsLow-bid median
1 to 1110$387.50
13 to 5811$235.00
69 to 16311$175.00
166 to 50511$195.00
Low strength mortar backfill, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Low strength mortar backfill
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
01 OCT 2026260433PUT505$191.00$200.006FENSON CONTRACTING LLCODOT
01 OCT 2026268019NOB84$115.00$135.004SHELLY & SANDS INCODOT
17 SEP 2026260416WIL128$285.00$250.003GEDDIS PAVING & EXCAVATING INCODOT
27 AUG 2026264020CAR155$140.00$189.002BOG CONSTRUCTION INCODOT
13 AUG 2026260364KNO100$200.00$192.004COMPLETE GENERAL CONSTRUCTION COMPANYODOT
25 JUN 2026268012VAN7$375.00$375.003PERRAM ELECTRIC INCODOT
07 MAY 2026260242JEF34$350.00$350.003MARUCCI & GAFFNEY EXCAVATING COODOT
23 APR 2026260142MEG369$225.00$198.004CAST & BAKER CORPORATIONODOT
09 APR 2026260187WYA5$250.00$307.246SMITH PAVING & EXCAVATING INCODOT
26 MAR 2026260124HAM2$1,000.00$1,373.802BARRETT PAVING MATERIALS INCODOT
26 MAR 2026260152HAS40$260.00$237.502SHELLY & SANDS INCODOT
26 MAR 2026260152HAS29$250.00$232.502SHELLY & SANDS INCODOT
26 MAR 2026260152HAS20$335.00$277.502SHELLY & SANDS INCODOT
12 MAR 2026260130NOB116$135.00$200.005J & J BRIDGE COMPANY INCODOT
19 FEB 2026260089MOT9$400.00$270.364L J DEWEESE CO INCODOT
Latest ODOT contracts carrying Low strength mortar backfill

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy