Parking lot stall marking unit price, Ohio
Low bidders on ODOT contracts carried a median of $2.00 per FT for item 644E01200, parking lot stall marking, over the 24 months to 12 NOV 2026, across 51 low bids. Half of all 144 bids fell between $1.94 and $3.35.
- Owner
- Ohio DOT
- Item
- 644E01200
- Unit
- FT
- Latest letting
- 29 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 19 | 19 | $2.00 | 61 | $2.00 |
| 2021 | 21 | 21 | $2.45 | 53 | $2.35 |
| 2022 | 37 | 37 | $2.50 | 85 | $2.55 |
| 2023 | 29 | 29 | $2.50 | 68 | $2.50 |
| 2024 | 17 | 17 | $2.50 | 49 | $2.40 |
| 2025 | 25 | 26 | $2.00 | 79 | $2.45 |
| 2026 | 26 | 25 | $2.25 | 65 | $2.25 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (FT) | Low bids | Low-bid median |
|---|---|---|
| 4 to 156 | 12 | $3.12 |
| 172 to 714 | 13 | $2.00 |
| 716 to 1,746 | 13 | $2.50 |
| 2,140 to 22,071 | 13 | $1.89 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 29 OCT 2026 | 260456 | COL | 238 | $6.50 | $4.25 | 2 | SHELLY & SANDS INC | ODOT |
| 15 OCT 2026 | 260484 | GAL | 7,526 | $1.85 | $2.25 | 3 | ALLARD EXCAVATION LLC | ODOT |
| 01 OCT 2026 | 260440 | AUG | 7,846 | $2.00 | $2.00 | 5 | HELMS AND SONS EXCAVATING | ODOT |
| 17 SEP 2026 | 260409 | JAC | 144 | $3.35 | $3.35 | 2 | SHELLY & SANDS INC | ODOT |
| 27 AUG 2026 | 260395 | GUE | 22,071 | $1.85 | $1.85 | 3 | NLS PAVING, INC | ODOT |
| 13 AUG 2026 | 260360 | DAR | 3,455 | $1.75 | $1.75 | 1 | WALLS BROS ASPHALT CO INC | ODOT |
| 13 AUG 2026 | 260364 | KNO | 10 | $3.00 | $3.00 | 4 | COMPLETE GENERAL CONSTRUCTION COMPANY | ODOT |
| 13 AUG 2026 | 260366 | MER | 70 | $10.00 | $10.00 | 1 | SHELLY COMPANY | ODOT |
| 16 JUL 2026 | 260326 | COS | 1,740 | $2.95 | $2.95 | 2 | SHELLY COMPANY | ODOT |
| 25 JUN 2026 | 260303 | ATH | 18,203 | $1.80 | $1.80 | 1 | SHELLY & SANDS INC | ODOT |
| 25 JUN 2026 | 260305 | BRO | 1,337 | $3.05 | $3.05 | 5 | FILLMORE CONSTRUCTION | ODOT |
| 25 JUN 2026 | 260311 | CUY | 400 | $2.00 | $4.00 | 4 | PERK COMPANY INC | ODOT |
| 25 JUN 2026 | 260312 | GUE | 1,435 | $2.50 | $2.50 | 2 | SHELLY & SANDS INC | ODOT |
| 21 MAY 2026 | 260273 | PUT | 130 | $3.00 | $3.00 | 2 | BLUFFTON PAVING INC | ODOT |
| 07 MAY 2026 | 260239 | HAR | 42 | $1.00 | $2.00 | 3 | EAGLE BRIDGE CO | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.