School symbol marking, 72" unit price, Ohio
Low bidders on ODOT contracts carried a median of $600.00 per EACH for item 644E01100, school symbol marking, 72", over the 24 months to 12 NOV 2026, across 17 low bids. Half of all 51 bids fell between $447.00 and $830.00.
- Owner
- Ohio DOT
- Item
- 644E01100
- Unit
- EACH
- Latest letting
- 17 SEP 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 4 | 4 | $572.50 | 16 | $522.50 |
| 2021 | 5 | 5 | $385.00 | 18 | $601.00 |
| 2022 | 6 | 6 | $727.50 | 15 | $556.50 |
| 2023 | 9 | 9 | $595.00 | 22 | $600.00 |
| 2024 | 8 | 8 | $792.50 | 16 | $725.00 |
| 2025 | 10 | 11 | $444.00 | 41 | $690.00 |
| 2026 | 5 | 5 | $780.00 | 9 | $780.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 4 | $715.00 |
| 2 to 2 | 4 | $325.00 |
| 2 to 2 | 4 | $725.00 |
| 2 to 4 | 5 | $450.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 17 SEP 2026 | 260410 | MAR | 4 | $780.00 | $590.00 | 2 | SHELLY & SANDS INC | ODOT |
| 27 AUG 2026 | 260378 | AUG | 2 | $300.00 | $597.50 | 2 | SHELLY COMPANY | ODOT |
| 07 MAY 2026 | 260254 | WIL | 2 | $800.00 | $800.00 | 1 | GERKEN PAVING INC | ODOT |
| 12 MAR 2026 | 260129 | MRW | 2 | $860.00 | $860.00 | 2 | KOKOSING CONSTRUCTION COMPANY INC | ODOT |
| 15 JAN 2026 | 260017 | HAM | 2 | $650.00 | $650.00 | 2 | BARRETT PAVING MATERIALS INC | ODOT |
| 18 DEC 2025 | 250587 | JEF | 4 | $425.00 | $412.50 | 2 | SHELLY & SANDS INC | ODOT |
| 18 DEC 2025 | 250600 | WAY | 2 | $444.00 | $497.00 | 2 | KOKOSING CONSTRUCTION COMPANY INC | ODOT |
| 04 DEC 2025 | 250530 | MAR | 2 | $350.00 | $500.00 | 5 | SHELLY & SANDS INC | ODOT |
| 04 DEC 2025 | 250560 | LAK | 2 | $800.00 | $850.00 | 5 | GREAT LAKES CRUSHING LTD | ODOT |
| 09 OCT 2025 | 250464 | HAM | 4 | $450.00 | $450.00 | 2 | JOHN R JURGENSEN COMPANY | ODOT |
| 09 OCT 2025 | 250475 | VAN | 2 | $300.00 | $500.00 | 2 | SHELLY COMPANY | ODOT |
| 09 OCT 2025 | 250475 | VAN | 2 | $300.00 | $500.00 | 2 | SHELLY COMPANY | ODOT |
| 27 MAR 2025 | 250170 | WIL | 2 | $800.00 | $800.00 | 1 | GERKEN PAVING INC | ODOT |
| 27 FEB 2025 | 250124 | LIC | 1 | $830.00 | $830.00 | 10 | MILLER BROS CONST INC | ODOT |
| 30 JAN 2025 | 250046 | DEL | 2 | $295.00 | $295.00 | 3 | SHELLY COMPANY | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way