Pedestal, 8', transformer base unit price, Ohio
Low bidders on ODOT contracts carried a median of $900.00 per EACH for item 632E89900, pedestal, 8', transformer base, over the 24 months to 12 NOV 2026, across 18 low bids. Half of all 54 bids fell between $850.00 and $1,207.50.
- Owner
- Ohio DOT
- Item
- 632E89900
- Unit
- EACH
- Latest letting
- 09 APR 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 7 | 7 | $655.50 | 25 | $650.00 |
| 2021 | 22 | 22 | $730.00 | 101 | $651.90 |
| 2022 | 12 | 12 | $1,045.00 | 37 | $955.00 |
| 2023 | 12 | 12 | $878.50 | 39 | $882.00 |
| 2024 | 8 | 8 | $912.00 | 24 | $950.00 |
| 2025 | 15 | 15 | $900.00 | 45 | $1,000.00 |
| 2026 | 2 | 2 | $1,082.50 | 7 | $1,200.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| HAM | 3 | $1,170.00 | 10 | $1,055.00 |
| District 3 | 3 | $900.00 | 7 | $1,019.00 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 4 | $1,199.91 |
| 2 to 4 | 5 | $850.00 |
| 5 to 8 | 4 | $1,063.97 |
| 9 to 20 | 5 | $900.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 09 APR 2026 | 260172 | District 4 | 8 | $865.00 | $1,100.00 | 5 | TC RANDEL CONSTRUCTON LLC | ODOT |
| 09 APR 2026 | 260176 | HAR | 5 | $1,300.00 | $1,671.50 | 2 | D L SMITH CONCRETE LLC | ODOT |
| 18 DEC 2025 | 250557 | HAM | 3 | $838.00 | $838.00 | 4 | EAGLE BRIDGE CO | ODOT |
| 04 DEC 2025 | 250556 | GEA | 1 | $1,354.05 | $1,354.05 | 3 | KARVO COMPANIES INC | ODOT |
| 04 DEC 2025 | 250569 | RIC | 3 | $750.00 | $875.00 | 2 | KOKOSING CONSTRUCTION COMPANY INC | ODOT |
| 09 OCT 2025 | 250478 | District 6 | 1 | $640.00 | $1,003.71 | 4 | PERRAM ELECTRIC INC | ODOT |
| 14 AUG 2025 | 250377 | CUY | 15 | $780.00 | $765.00 | 6 | CATTS CONSTRUCTION INC | ODOT |
| 17 JUL 2025 | 250352 | District 7 | 8 | $1,262.95 | $1,262.95 | 1 | CAPITAL ELECTRIC LINE BUILDERS INC | ODOT |
| 15 MAY 2025 | 250262 | SUM | 2 | $850.00 | $1,425.00 | 4 | KARVO COMPANIES INC | ODOT |
| 08 MAY 2025 | 250244 | District 3 | 20 | $900.00 | $900.00 | 3 | CORNERSTONE ELECTRIC INC | ODOT |
| 08 MAY 2025 | 250250 | HAM | 9 | $1,170.00 | $1,115.00 | 2 | PRUS CONSTRUCTION COMPANY | ODOT |
| 08 MAY 2025 | 250256 | MAH | 3 | $1,000.00 | $900.00 | 2 | CORNERSTONE ELECTRIC INC | ODOT |
| 24 APR 2025 | 250216 | District 8 | 10 | $890.00 | $945.00 | 2 | MILLER CABLE COMPANY | ODOT |
| 10 APR 2025 | 250191 | District 3 | 18 | $900.00 | $971.05 | 2 | PERK COMPANY INC | ODOT |
| 27 FEB 2025 | 250134 | SUM | 5 | $859.00 | $896.60 | 4 | SHELLY & SANDS INC | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.