Pedestal, 8', transformer base, as per plan unit price, Ohio
Low bidders on ODOT contracts carried a median of $1,133.00 per EACH for item 632E89901, pedestal, 8', transformer base, as per plan, over the 24 months to 12 NOV 2026, across 11 low bids. Half of all 36 bids fell between $959.25 and $1,300.00.
- Owner
- Ohio DOT
- Item
- 632E89901
- Unit
- EACH
- Latest letting
- 26 MAR 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 4 | 4 | $962.50 | 16 | $834.50 |
| 2021 | 17 | 18 | $845.00 | 72 | $875.00 |
| 2022 | 12 | 12 | $987.22 | 41 | $959.44 |
| 2023 | 4 | 4 | $1,155.06 | 15 | $1,050.00 |
| 2024 | 5 | 5 | $1,150.00 | 17 | $1,160.00 |
| 2025 | 7 | 7 | $1,050.00 | 26 | $1,050.00 |
| 2026 | 3 | 3 | $1,320.59 | 8 | $1,337.80 |
Bid prices as published, not adjusted for inflation.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 26 MAR 2026 | 260121 | HAM | 3 | $1,320.59 | $1,310.30 | 4 | SUNESIS CONSTRUCTION CO | ODOT |
| 26 MAR 2026 | 260143 | AUG | 5 | $1,355.00 | $1,377.50 | 2 | MILLER CONTRACTING GROUP INC | ODOT |
| 29 JAN 2026 | 260064 | POR | 2 | $900.00 | $1,321.90 | 2 | KARVO COMPANIES INC | ODOT |
| 11 SEP 2025 | 250411 | HAM | 1 | $1,375.00 | $1,100.00 | 5 | FORD DEVELOPMENT CORP | ODOT |
| 17 JUL 2025 | 250343 | CUY | 10 | $912.00 | $943.50 | 4 | PERRAM ELECTRIC INC | ODOT |
| 17 JUL 2025 | 250348 | RIC | 7 | $440.00 | $440.00 | 1 | SHELLY & SANDS INC | ODOT |
| 22 MAY 2025 | 258009 | AUG | 9 | $1,133.00 | $1,133.00 | 5 | PERRAM ELECTRIC INC | ODOT |
| 24 APR 2025 | 250210 | ATB | 4 | $1,149.00 | $1,149.00 | 1 | CATTS CONSTRUCTION INC | ODOT |
| 13 FEB 2025 | 250077 | ROS | 32 | $500.00 | $175.00 | 3 | COMPLETE GENERAL CONSTRUCTION COMPANY | ODOT |
| 30 JAN 2025 | 250060 | MOT | 2 | $1,050.00 | $1,108.69 | 7 | BARRETT PAVING MATERIALS INC | ODOT |
| 19 DEC 2024 | 240572 | CLE | 2 | $1,180.00 | $1,590.00 | 2 | BANSAL CONSTRUCTION INC | ODOT |
| 16 MAY 2024 | 240269 | HAM | 2 | $1,160.00 | $1,160.00 | 3 | JOHN R JURGENSEN COMPANY | ODOT |
| 22 FEB 2024 | 240107 | SUM | 7 | $1,100.00 | $1,100.00 | 5 | KENMORE CONSTRUCTION CO INC | ODOT |
| 22 FEB 2024 | 240139 | HAM | 3 | $1,080.00 | $1,080.00 | 5 | BARRETT PAVING MATERIALS INC | ODOT |
| 08 FEB 2024 | 240121 | LAK | 8 | $1,150.00 | $1,176.88 | 2 | ECLIPSE CO LLC | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.