Removal of overhead mounted sign and reerection unit price, Ohio
Low bidders on ODOT contracts carried a median of $707.50 per EACH for item 630E87100, removal of overhead mounted sign and reerection, over the 24 months to 12 NOV 2026, across 14 low bids. Half of all 31 bids fell between $407.50 and $1,175.00.
- Owner
- Ohio DOT
- Item
- 630E87100
- Unit
- EACH
- Latest letting
- 15 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 8 | 8 | $452.50 | 28 | $452.50 |
| 2021 | 10 | 11 | $335.00 | 55 | $325.00 |
| 2022 | 14 | 14 | $525.00 | 54 | $462.50 |
| 2023 | 9 | 9 | $750.00 | 27 | $700.00 |
| 2024 | 9 | 9 | $425.00 | 24 | $400.00 |
| 2025 | 7 | 7 | $765.00 | 20 | $565.50 |
| 2026 | 6 | 6 | $605.00 | 10 | $650.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 3 | $1,200.00 |
| 1 to 3 | 4 | $472.50 |
| 3 to 3 | 3 | $525.00 |
| 4 to 5 | 4 | $907.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 15 OCT 2026 | 260478 | District 4 | 3 | $525.00 | $525.00 | 1 | LAKE ERIE CONSTRUCTION COMPANY | ODOT |
| 08 OCT 2026 | 260398 | HAM | 2 | $2,406.42 | $2,406.42 | 1 | JOHN R JURGENSEN COMPANY | ODOT |
| 07 MAY 2026 | 260260 | LUC | 1 | $385.00 | $385.00 | 1 | MILLER BROS CONST INC | ODOT |
| 26 MAR 2026 | 260076 | MAH | 1 | $2,420.00 | $2,420.00 | 3 | KARVO COMPANIES INC | ODOT |
| 19 FEB 2026 | 260082 | District 10 | 1 | $650.00 | $487.50 | 2 | M P DORY CO | ODOT |
| 15 JAN 2026 | 260034 | District 3 | 2 | $560.00 | $605.00 | 2 | CLEVELAND BARRICADING SYSTEMS LLC | ODOT |
| 18 DEC 2025 | 250610 | CUY | 4 | $1,050.00 | $525.00 | 5 | GREAT LAKES CONSTRUCTION CO | ODOT |
| 13 NOV 2025 | 250539 | District 2 | 3 | $430.00 | $430.00 | 1 | LAKE ERIE CONSTRUCTION COMPANY | ODOT |
| 23 OCT 2025 | 250500 | LAK | 1 | $1,200.00 | $1,200.00 | 3 | J D WILLIAMSON CONSTRUCTION CO INC | ODOT |
| 17 JUL 2025 | 250343 | CUY | 4 | $285.00 | $262.50 | 4 | PERRAM ELECTRIC INC | ODOT |
| 27 FEB 2025 | 250076 | FRA | 3 | $1,250.00 | $1,250.00 | 1 | SHELLY & SANDS INC | ODOT |
| 30 JAN 2025 | 250002 | LAK | 5 | $765.00 | $803.25 | 2 | GREAT LAKES CONSTRUCTION CO | ODOT |
| 16 JAN 2025 | 250013 | HAM | 3 | $125.00 | $653.97 | 4 | PRUS CONSTRUCTION COMPANY | ODOT |
| 14 NOV 2024 | 240517 | CUY | 4 | $2,155.00 | $2,155.00 | 1 | GREAT LAKES CONSTRUCTION CO | ODOT |
| 27 JUN 2024 | 240358 | TRU | 2 | $1,500.00 | $930.00 | 5 | CORNERSTONE ELECTRIC INC | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.