Removal of structure mounted sign and disposal unit price, Ohio
Low bidders on ODOT contracts carried a median of $435.00 per EACH for item 630E86310, removal of structure mounted sign and disposal, over the 24 months to 12 NOV 2026, across 12 low bids. Half of all 29 bids fell between $325.00 and $550.00.
- Owner
- Ohio DOT
- Item
- 630E86310
- Unit
- EACH
- Latest letting
- 25 JUN 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 9 | 9 | $244.00 | 37 | $250.00 |
| 2021 | 4 | 4 | $300.00 | 14 | $350.00 |
| 2022 | 4 | 4 | $225.00 | 14 | $250.00 |
| 2023 | 6 | 6 | $312.50 | 16 | $275.00 |
| 2024 | 6 | 6 | $207.50 | 15 | $250.00 |
| 2025 | 7 | 7 | $475.00 | 18 | $487.50 |
| 2026 | 5 | 5 | $385.00 | 11 | $385.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 3 | $475.00 |
| 1 to 2 | 3 | $551.25 |
| 2 to 3 | 3 | $550.00 |
| 5 to 43 | 3 | $325.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 25 JUN 2026 | 260319 | FRA | 3 | $550.00 | $550.00 | 3 | RUHLIN COMPANY | ODOT |
| 11 JUN 2026 | 260293 | CUY | 1 | $385.00 | $385.00 | 3 | RUHLIN COMPANY | ODOT |
| 26 MAR 2026 | 260159 | CUY | 43 | $325.00 | $325.00 | 1 | LAKE ERIE CONSTRUCTION COMPANY | ODOT |
| 19 FEB 2026 | 260082 | District 10 | 5 | $300.00 | $287.50 | 2 | M P DORY CO | ODOT |
| 15 JAN 2026 | 260034 | District 3 | 2 | $725.00 | $485.00 | 2 | CLEVELAND BARRICADING SYSTEMS LLC | ODOT |
| 04 DEC 2025 | 250549 | COL | 1 | $551.25 | $594.05 | 4 | BCC OHIO INC | ODOT |
| 13 NOV 2025 | 250539 | District 2 | 2 | $750.00 | $750.00 | 1 | LAKE ERIE CONSTRUCTION COMPANY | ODOT |
| 15 MAY 2025 | 250238 | HAM | 1 | $475.00 | $475.00 | 2 | JOHN R JURGENSEN COMPANY | ODOT |
| 08 MAY 2025 | 250268 | District 12 | 1 | $320.00 | $410.00 | 2 | LAKE ERIE CONSTRUCTION COMPANY | ODOT |
| 13 FEB 2025 | 250077 | ROS | 10 | $395.00 | $400.00 | 3 | COMPLETE GENERAL CONSTRUCTION COMPANY | ODOT |
| 13 FEB 2025 | 250110 | District 10 | 3 | $300.00 | $287.50 | 2 | M P DORY CO | ODOT |
| 16 JAN 2025 | 250013 | HAM | 1 | $502.00 | $676.00 | 4 | PRUS CONSTRUCTION COMPANY | ODOT |
| 18 APR 2024 | 244011 | WOO | 1 | $145.00 | $147.50 | 4 | ADVANCED EXCAVATING & DEMOLITION LLC | ODOT |
| 04 APR 2024 | 240168 | COL | 3 | $165.00 | $165.00 | 3 | A P O'HORO COMPANY | ODOT |
| 04 APR 2024 | 240204 | BEL | 8 | $145.00 | $222.50 | 2 | LAKE ERIE CONSTRUCTION COMPANY | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.