Work zone arrow, class i unit price, Ohio

Low bidders on ODOT contracts carried a median of $60.10 per EACH for item 614E30000, work zone arrow, class i, over the 24 months to 12 NOV 2026, across 32 low bids. Half of all 112 bids fell between $47.75 and $100.00.

Owner
Ohio DOT
Item
614E30000
Unit
EACH
Latest letting
29 OCT 2026
$60.10Low bidder's median, per EACH
$75.00Median of all bids, per EACH
32Contracts in the window

By year of letting

Work zone arrow, class i, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20201112$52.5052$55.00
20212525$55.00123$55.00
20221516$75.0054$75.00
20231919$100.0063$100.00
202499$100.0035$85.00
20251111$59.0045$70.00
20262020$58.1065$75.00
Work zone arrow, class i, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Work zone arrow, class i, ODOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
CUY4$47.5014$49.00
HAM3$45.0011$55.00
FRA3$80.007$100.00
Work zone arrow, class i, ODOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Work zone arrow, class i, ODOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
2 to 68$72.00
6 to 198$72.50
22 to 488$72.50
52 to 1568$46.00
Work zone arrow, class i, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Work zone arrow, class i
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
29 OCT 2026260399CUY93$45.00$41.004TRI-MOR CORPODOT
29 OCT 2026260468MAH15$100.00$100.004SHELLY & SANDS INCODOT
01 OCT 2026260405DEL24$75.00$75.003SHELLY & SANDS INCODOT
13 AUG 2026260364KNO17$75.00$75.004COMPLETE GENERAL CONSTRUCTION COMPANYODOT
13 AUG 2026260368PIK53$135.00$135.009ALLARD EXCAVATION LLCODOT
30 JUL 2026260354MAH95$55.00$57.004MARUCCI & GAFFNEY EXCAVATING COODOT
07 MAY 2026260167ERI86$50.00$50.003GREAT LAKES DEMOLITION COMPANYODOT
07 MAY 2026260227AUG22$52.00$55.003HELMS AND SONS EXCAVATINGODOT
07 MAY 2026260232CUY57$40.00$40.003PERK COMPANY INCODOT
07 MAY 2026260237FRA43$80.00$97.502SHELLY & SANDS INCODOT
07 MAY 2026260261MIA6$30.00$70.052BRUMBAUGH CONSTRUCTION INCODOT
23 APR 2026260214SAN41$61.20$60.003ERIE BLACKTOP INCODOT
23 APR 2026260221FRA22$80.00$97.502COMPLETE GENERAL CONSTRUCTION COMPANYODOT
09 APR 2026260180MOT2$115.00$107.504CAPITAL ELECTRIC LINE BUILDERS INCODOT
26 MAR 2026260143AUG8$46.00$46.002MILLER CONTRACTING GROUP INCODOT
Latest ODOT contracts carrying Work zone arrow, class i

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way