Work zone crosswalk line, class i, 12", 642 paint unit price, Ohio
Low bidders on ODOT contracts carried a median of $2.20 per FT for item 614E27050, work zone crosswalk line, class i, 12", 642 paint, over the 24 months to 12 NOV 2026, across 20 low bids. Half of all 73 bids fell between $1.85 and $3.00.
- Owner
- Ohio DOT
- Item
- 614E27050
- Unit
- FT
- Latest letting
- 30 JUL 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2021 | 2 | 2 | $1.02 | 7 | $1.03 |
| 2022 | 7 | 7 | $2.25 | 28 | $2.25 |
| 2023 | 14 | 14 | $2.50 | 47 | $2.50 |
| 2024 | 11 | 12 | $2.12 | 41 | $2.80 |
| 2025 | 12 | 12 | $2.83 | 43 | $2.65 |
| 2026 | 6 | 6 | $2.08 | 24 | $2.15 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| LAK | 4 | $2.38 | 22 | $3.00 |
| CUY | 5 | $2.25 | 16 | $2.58 |
| GEA | 3 | $1.25 | 15 | $1.85 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (FT) | Low bids | Low-bid median |
|---|---|---|
| 74 to 230 | 5 | $2.25 |
| 238 to 501 | 5 | $2.50 |
| 533 to 1,095 | 5 | $1.50 |
| 1,260 to 4,985 | 5 | $2.15 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 30 JUL 2026 | 260347 | FAY | 1,260 | $2.00 | $2.00 | 2 | JOHN R JURGENSEN COMPANY | ODOT |
| 25 JUN 2026 | 260308 | CUY | 190 | $2.25 | $2.25 | 3 | KOKOSING CONSTRUCTION COMPANY INC | ODOT |
| 25 JUN 2026 | 260310 | CUY | 1,468 | $2.50 | $2.50 | 4 | RONYAK PAVING INC | ODOT |
| 12 MAR 2026 | 260120 | GEA | 74 | $1.85 | $1.85 | 4 | RONYAK PAVING INC | ODOT |
| 29 JAN 2026 | 260057 | LAK | 4,182 | $1.75 | $1.75 | 7 | GEAUGA HIGHWAY CO | ODOT |
| 15 JAN 2026 | 260013 | District 12 | 1,587 | $2.15 | $2.15 | 4 | KARVO COMPANIES INC | ODOT |
| 18 DEC 2025 | 250561 | LAK | 533 | $3.00 | $3.00 | 7 | SPECIALIZED CONSTRUCTION INC | ODOT |
| 18 DEC 2025 | 250582 | CUY | 452 | $2.65 | $2.65 | 3 | KOKOSING CONSTRUCTION COMPANY INC | ODOT |
| 18 DEC 2025 | 250588 | LAK | 910 | $1.45 | $1.98 | 6 | RONYAK PAVING INC | ODOT |
| 13 NOV 2025 | 250519 | District 7 | 1,095 | $5.00 | $3.75 | 2 | WARD CONSTRUCTION CO | ODOT |
| 23 OCT 2025 | 250497 | GEA | 765 | $1.25 | $1.25 | 5 | RONYAK PAVING INC | ODOT |
| 09 OCT 2025 | 250463 | GRE | 238 | $1.80 | $1.80 | 1 | STRAWSER CONSTRUCTION INC | ODOT |
| 25 SEP 2025 | 250430 | BUT | 140 | $3.00 | $3.00 | 2 | JOHN R JURGENSEN COMPANY | ODOT |
| 25 SEP 2025 | 250436 | GEA | 96 | $1.20 | $2.50 | 6 | RONYAK PAVING INC | ODOT |
| 15 MAY 2025 | 250238 | HAM | 378 | $3.50 | $3.50 | 2 | JOHN R JURGENSEN COMPANY | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.