Work zone crossover lighting system unit price, Ohio

Low bidders on ODOT contracts carried a median of $39,085 per EACH for item 614E12756, work zone crossover lighting system, over the 24 months to 12 NOV 2026, across 18 low bids. Half of all 53 bids fell between $31,000 and $51,000.

Owner
Ohio DOT
Item
614E12756
Unit
EACH
Latest letting
08 OCT 2026
$39,085Low bidder's median, per EACH
$43,000Median of all bids, per EACH
18Contracts in the window

By year of letting

Work zone crossover lighting system, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202077$22,00027$26,750
202177$29,50035$30,000
202244$35,00016$35,000
20231111$35,00036$36,000
202488$32,15818$36,200
202588$41,50028$47,875
202688$39,68521$41,200
Work zone crossover lighting system, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By quantity

Work zone crossover lighting system, ODOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 14$45,000
1 to 25$38,170
2 to 44$34,600
4 to 205$28,115
Work zone crossover lighting system, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Work zone crossover lighting system
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
08 OCT 2026260398HAM2$55,348$55,3481JOHN R JURGENSEN COMPANYODOT
07 MAY 2026260227AUG1$76,000$52,7183HELMS AND SONS EXCAVATINGODOT
07 MAY 2026260237FRA2$31,000$30,7502SHELLY & SANDS INCODOT
07 MAY 2026260251MOT3$41,200$41,2002JOHN R JURGENSEN COMPANYODOT
26 FEB 2026260041LIC1$50,000$77,5002KOKOSING CONSTRUCTION COMPANY INCODOT
19 FEB 2026260096SUM2$38,170$39,0854KENMORE CONSTRUCTION CO INCODOT
05 FEB 2026260003MAH1$35,000$35,0004SHELLY & SANDS INCODOT
29 JAN 2026260002HEN20$24,750$24,7503E S WAGNER - VERNON NAGEL JOINT VENTUREODOT
23 OCT 2025250459CRA2$51,000$53,0004SHELLY & SANDS INCODOT
15 MAY 2025250238HAM2$32,525$32,5252JOHN R JURGENSEN COMPANYODOT
17 APR 2025250151FRA3$28,000$29,0004COMPLETE GENERAL CONSTRUCTION COMPANYODOT
10 APR 2025250186ATH1$82,000$82,0001KOKOSING CONSTRUCTION COMPANY INCODOT
27 MAR 2025250150UNI4$43,000$43,0004MILLER BROS CONST INCODOT
27 FEB 2025250004SUM4$27,500$27,5003KENMORE CONSTRUCTION CO INCODOT
27 FEB 2025250128MEG1$40,000$48,7506KOKOSING CONSTRUCTION COMPANY INCODOT
Latest ODOT contracts carrying Work zone crossover lighting system

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy