Work zone lighting system unit price, Ohio

Low bidders on ODOT contracts carried a median of $5,000.00 per EACH for item 614E12740, work zone lighting system, over the 24 months to 12 NOV 2026, across 31 low bids. Half of all 136 bids fell between $2,200.00 and $16,056.

Owner
Ohio DOT
Item
614E12740
Unit
EACH
Latest letting
01 OCT 2026
$5,000.00Low bidder's median, per EACH
$5,250.00Median of all bids, per EACH
33Contracts in the window

By year of letting

Work zone lighting system, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20203633$7,300.00211$7,500.00
20213329$5,000.00180$6,000.00
20222723$4,000.00120$3,250.00
20231917$9,450.0073$7,000.00
20242421$3,600.00106$5,506.25
20251816$3,600.0070$5,000.00
20261212$10,50052$7,500.00
Work zone lighting system, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Work zone lighting system, ODOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
GAL4$1,050.0018$5,000.00
WAS5$11,00017$10,000
NOB3$35,00015$12,500
BEL3$2,000.0012$4,015.05
Work zone lighting system, ODOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Work zone lighting system, ODOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 17$3,500.00
1 to 18$10,500
1 to 28$3,500.00
2 to 88$7,550.50
Work zone lighting system, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Work zone lighting system
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
01 OCT 2026260429MED1$2,000.00$2,205.486FECHKO EXCAVATING LLCODOT
01 OCT 2026260438VIN1$50,000$15,0007FILLMORE CONSTRUCTIONODOT
01 OCT 2026268019NOB1$80,000$15,3504SHELLY & SANDS INCODOT
17 SEP 2026264023BEL2$2,000.00$2,100.002J & J BRIDGE COMPANY INCODOT
13 AUG 2026260359BEL2$4,101.00$5,800.502BCC OHIO INCODOT
13 AUG 2026260361GAL1$7,500.00$7,500.003AXIS CIVIL CONSTRUCTION LLCODOT
13 AUG 2026260362HAS1$2,000.00$5,250.006DENNISON BRIDGE INCODOT
13 AUG 2026260368PIK1$16,056$16,1009ALLARD EXCAVATION LLCODOT
21 MAY 2026264014WAS1$10,000$5,750.004R C CONSTRUCTION COMPANY AND SON INCODOT
23 APR 2026260142MEG4$11,000$3,086.004CAST & BAKER CORPORATIONODOT
09 APR 2026260185WAS1$11,000$6,550.753SHELLY & SANDS INCODOT
29 JAN 2026260068WAS1$39,000$32,0002SHELLY & SANDS INCODOT
04 DEC 2025250559HOC8$500.00$1,000.005COMPLETE GENERAL CONSTRUCTION COMPANYODOT
13 NOV 2025250527JEF2$15,000$15,0003BUDS INCODOT
13 NOV 2025250532NOB2$35,000$10,0007BUDS INCODOT
Latest ODOT contracts carrying Work zone lighting system

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy