ODOT contract 15589 bid tabulation
May street elevated sidewalk replacement. Let by Oregon DOT on February 27, 2025, Region 1. 5 bids received.
- Owner
- Oregon DOT
- Letting
- 27 FEB 2025
- Pay items
- 68
- Data through
- 13 AUG 2026
Bidders
| Rank | Total bid | Against the low bid |
|---|---|---|
| 1 | Low | |
| 2 | ||
| 3 | ||
| 4 | ||
| 5 |
Bid tabulation
| Line | Pay item | Unit | Quantity | Rank 1 | Rank 2 | Rank 3 | Rank 4 | Rank 5 |
|---|---|---|---|---|---|---|---|---|
| 1 | Removal of inlets (0310-0104000E) | EACH | 1 | $1,500.00 | $1,500.00 | $1,200.00 | $1,730.00 | $2,000.00 |
| 2 | 10 inch sanitary sewer pipe, 10 FT depth (0445-030010BF) | LF | 84 | $320.00 | $400.00 | $175.00 | $400.00 | $400.00 |
| 3 | Temporary curb ramp, constructed (0228-0167670E) | EACH | 3 | $5,000.00 | $4,600.00 | $4,000.00 | $570.00 | $750.00 |
| 4 | 10 inch sanitary sewer pipe, 20 FT depth (0445-030010CF) | LF | 32 | $400.00 | $800.00 | $260.00 | $700.00 | $1,000.00 |
| 5 | Concrete curbs, curb and gutter (0759-0103000F) | LF | 340 | $55.00 | $70.00 | $75.00 | $59.00 | $40.00 |
| 6 | Concrete sanitary sewer manholes (0470-0100000E) | EACH | 2 | $7,500.00 | $18,000 | $20,000 | $15,000 | $15,000 |
| 7 | Wall drainage and filter system (0596-D004000A) | LS | 1 | $150,000 | $60,000 | $17,000 | $55,000 | $36,000 |
| 8 | Metal handrail, two rails (1069-0100000F) | LF | 257 | $100.00 | $100.00 | $200.00 | $190.00 | $60.00 |
| 9 | Asphalt pavement sawcutting (0310-0119000F) | LF | 384 | $6.00 | $7.00 | $2.00 | $8.90 | $10.00 |
| 10 | Membrane separator (1999-9Z90000I) | SY | 1,010 | $35.00 | $40.00 | $10.00 | $50.00 | $60.00 |
| 11 | Temporary seeding (1030-0103000R) | ACRE | 0.10 | $20,000 | $20,000 | $20,000 | $1,670.00 | $19,000 |
| 12 | Pedestrian channelizing devices (0228-0141600F) | LF | 338 | $30.00 | $32.00 | $20.00 | $19.50 | $50.00 |
| 13 | Temporary barrier (0226-0126100F) | LF | 245 | $35.00 | $45.00 | $20.00 | $36.25 | $32.50 |
| 14 | Perforated steel square tube anchor sign supports (0930-0117000A) | LB | 294.60 | $10.18 | $13.58 | $11.88 | $13.58 | $8.49 |
| 15 | Sign support footings (0920-0100000A) | CY | 0.60 | $8,333.33 | $16,667 | $16,000 | $16,667 | $4,166.67 |
| 16 | Mainline video inspection (0415-0100000F) | LF | 30 | $75.00 | $45.00 | $75.00 | $84.00 | $100.00 |
| 17 | Sediment fence (0280-0113000F) | LF | 295 | $6.00 | $6.00 | $15.00 | $8.50 | $5.00 |
| 18 | 3/4 inch - 0 aggregate base (0641-0112000M) | TON | 150 | $100.00 | $90.00 | $250.00 | $85.00 | $58.00 |
| 19 | Temporary walks (0228-0167680J) | SF | 375 | $12.00 | $10.00 | $23.00 | $16.75 | $20.00 |
| 20 | Temporary plastic drums (0224-0145000E) | EACH | 24 | $30.00 | $75.00 | $200.00 | $32.00 | $50.00 |
| 21 | Removal of structures and obstructions (0310-0106000A) | LS | 1 | $100,000 | $110,000 | $38,000 | $15,000 | $300,000 |
| 22 | Lightweight retaining wall backfill (1999-9Z90000K) | CY | 447 | $1.00 | $235.00 | $350.00 | $200.00 | $282.00 |
| 23 | Perforated steel square tube slip base sign supports (0930-0114000A) | LB | 68.20 | $11.73 | $29.33 | $19.06 | $21.99 | $36.66 |
| 24 | General structural concrete, class 4000 (0540-0312000K) | CY | 45 | $800.00 | $1,800.00 | $2,200.00 | $2,200.00 | $2,500.00 |
| 25 | Reinforcement, grade 60 (0530-0104000O) | LB | 7,750 | $2.00 | $1.75 | $2.00 | $3.40 | $4.00 |
| 26 | Temporary barricades, type II (0224-0104000E) | EACH | 8 | $25.00 | $75.00 | $250.00 | $67.00 | $150.00 |
| 27 | Extra for new curb ramps (0759-0154100E) | EACH | 2 | $2,500.00 | $2,000.00 | $3,700.00 | $1,720.00 | $800.00 |
| 28 | Temporary barricades, type III (0224-0105000E) | EACH | 13 | $125.00 | $275.00 | $600.00 | $180.00 | $150.00 |
| 29 | Pavement legend, type B-HS: disabled parking (0867-0173100E) | EACH | 1 | $650.00 | $800.00 | $650.00 | $730.00 | $650.00 |
| 30 | Removal of manholes (0310-0105000E) | EACH | 2 | $2,000.00 | $4,000.00 | $1,500.00 | $3,280.00 | $3,000.00 |
| 31 | General excavation (0330-0105000K) | CY | 340 | $85.00 | $100.00 | $100.00 | $90.00 | $60.00 |
| 32 | Traffic control supervisor (0223-0169000E) | EACH | 109 | $250.00 | $600.00 | $1,375.00 | $1,117.00 | $43.00 |
| 33 | Concrete inlets, type G-2 (0470-0315000E) | EACH | 2 | $8,500.00 | $4,750.00 | $10,000 | $4,460.00 | $6,000.00 |
| 34 | 1-1/2 inch - 0 aggregate base (0641-0117000M) | TON | 300 | $60.00 | $40.00 | $125.00 | $55.00 | $57.00 |
| 35 | Flaggers (0223-0168000T) | HR | 312 | $75.00 | $82.00 | $90.00 | $97.00 | $80.00 |
| 36 | Signs, standard sheeting, sheet aluminum (0940-0202000J) | SF | 32.50 | $40.00 | $50.00 | $58.00 | $56.00 | $50.00 |
| 37 | Stripe removal (0225-0154000F) | LF | 340 | $3.00 | $3.25 | $3.00 | $3.40 | $3.00 |
| 38 | Inlet protection, type 7 (0280-0114070E) | EACH | 1 | $75.00 | $100.00 | $1,000.00 | $110.00 | $250.00 |
| 39 | Removal of curbs (0310-0101000F) | LF | 322 | $10.00 | $10.00 | $10.00 | $23.00 | $10.00 |
| 40 | Removal of pipes (0310-0100000F) | LF | 178 | $15.00 | $50.00 | $35.00 | $36.50 | $170.00 |
| 41 | Clearing and grubbing (0320-0100000R) | ACRE | 0.10 | $35,000 | $90,000 | $15,000 | $26,200 | $90,000 |
| 42 | Removal of walks and driveways (0310-0102000J) | SY | 387 | $100.00 | $25.00 | $25.00 | $58.00 | $15.00 |
| 43 | Pavement legend, type B-HS: arrows (0867-0103100E) | EACH | 2 | $375.00 | $400.00 | $375.00 | $420.00 | $375.00 |
| 44 | Pavement legend, type B-HS: bicycle lane stencil (0867-0131000E) | EACH | 1 | $375.00 | $400.00 | $375.00 | $420.00 | $375.00 |
| 45 | Truncated domes on new surfaces (0759-0510000J) | SF | 22 | $50.00 | $40.00 | $75.00 | $1.40 | $40.00 |
| 46 | Thermoplastic, extruded, surface, non-profiled (0865-0116610F) | LF | 900 | $4.25 | $4.75 | $4.25 | $4.70 | $4.25 |
| 47 | Pavement bar, type B-HS (0867-0145100J) | SF | 210 | $18.85 | $20.00 | $18.85 | $21.00 | $18.85 |
| 48 | Concrete driveways (0759-0126000J) | SF | 330 | $15.00 | $32.00 | $20.00 | $24.00 | $11.00 |
| 49 | 8 inch storm sewer pipe, 20 FT depth (0445-035008CF) | LF | 20 | $450.00 | $600.00 | $425.00 | $750.00 | $1,000.00 |
| 50 | Bar removal (0225-0156000J) | SF | 225 | $15.00 | $16.00 | $15.00 | $16.75 | $15.00 |
| 51 | HP 14 X 89 steel soldier piles (0596-D002000F) | LF | 940 | $75.00 | $67.00 | $85.00 | $85.00 | $78.00 |
| 52 | Curb marking, paint (0869-0200000F) | LF | 130 | $5.00 | $5.50 | $5.00 | $5.60 | $3.00 |
| 53 | Inlet protection, type 3 (0280-0114030E) | EACH | 7 | $60.00 | $125.00 | $300.00 | $63.00 | $100.00 |
| 54 | Concrete walks (0759-0128000J) | SF | 4,700 | $8.00 | $13.50 | $15.00 | $17.00 | $11.00 |
| 55 | Remove existing signs (0905-0100000A) | LS | 1 | $600.00 | $500.00 | $1,500.00 | $220.00 | $500.00 |
| 56 | Level 2, 1/2 inch ACP mixture (0744-0202000M) | TON | 157 | $160.00 | $248.00 | $280.00 | $180.00 | $165.00 |
| 57 | Adjusting boxes (0490-0100000E) | EACH | 1 | $500.00 | $500.00 | $2,500.00 | $100.00 | $1,000.00 |
| 58 | 8 inch storm sewer pipe, 10 FT depth (0445-035008BF) | LF | 10 | $200.00 | $725.00 | $312.00 | $650.00 | $1,000.00 |
| 59 | Retaining wall, cast-in-place concrete semi-gravity cantilever (0596-C003000A) | SF | 210.76 | $355.86 | $474.47 | $521.92 | $427.03 | $474.47 |
| 60 | Predrilling and encasing soldier piles (0596-D001000F) | LF | 867 | $350.00 | $360.00 | $335.00 | $360.00 | $360.00 |
| 61 | Legend removal (0225-0155100J) | SF | 2 | $200.00 | $225.00 | $200.00 | $220.00 | $200.00 |
| 62 | Granular structure backfill (0510-0108000K) | CY | 180 | $85.00 | $115.00 | $150.00 | $100.00 | $250.00 |
| 63 | Portable changeable message signs (0222-0164000E) | EACH | 2 | $3,000.00 | $7,500.00 | $12,500 | $6,880.00 | $10,000 |
| 64 | Lagging (0596-D003000J) | SF | 1,600 | $40.00 | $40.00 | $95.00 | $85.00 | $72.00 |
| 65 | Temporary signs (0222-0102000J) | SF | 263 | $35.00 | $35.00 | $30.00 | $24.00 | $40.00 |
| 66 | Temporary impact attenuator, narrow site system (0226-0134000E) | EACH | 1 | $3,500.00 | $3,500.00 | $7,500.00 | $5,000.00 | $3,500.00 |
| 67 | Pollution control plan (0290-0100000A) | LS | 1 | $1,200.00 | $3,000.00 | $1,500.00 | $1,120.00 | $250.00 |
| 68 | Structure excavation (0510-0101000K) | CY | 560 | $85.00 | $75.00 | $125.00 | $90.00 | $70.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Bid Data Program yearly workbooks. ODOT publishes rank and unit price only: no bidder names and no bid totals, so these bids cannot be checked against a total and Oregon is left out of the competitor views.
Every contract let that day: ODOT letting of February 27, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way