ODOT contract 15609 bid tabulation
Odot fleet charging equipment. Let by Oregon DOT on September 25, 2025, Region 4. 2 bids received.
- Owner
- Oregon DOT
- Letting
- 25 SEP 2025
- Pay items
- 24
- Data through
- 13 AUG 2026
Bidders
| Rank | Total bid | Against the low bid |
|---|---|---|
| 1 | Low | |
| 2 |
Bid tabulation
| Line | Pay item | Unit | Quantity | Rank 1 | Rank 2 |
|---|---|---|---|---|---|
| 1 | Longitudinal pavement markings - paint (0860-0200000F) | LF | 200 | $15.00 | $39.37 |
| 2 | Asphalt pavement sawcutting, 6 inches deep (0310-0119100F) | LF | 760 | $10.00 | $5.00 |
| 3 | Sign support footings (0920-0100000A) | CY | 0.40 | $17,500 | $5,214.97 |
| 4 | Furnish level 2 EV chargers, corvallis (1999-9Z90000E) | EACH | 1 | $25,000 | $35,000 |
| 5 | Furnish DCFC EV chargers, bend (1999-9Z90000E) | EACH | 1 | $157,250 | $232,000 |
| 6 | Furnish level 2 EV chargers, bend (1999-9Z90000E) | EACH | 2 | $25,000 | $33,000 |
| 7 | Pollution control plan (0290-0100000A) | LS | 1 | $500.00 | $3,000.00 |
| 8 | Furnish DCFC EV chargers, roseburg (1999-9Z90000E) | EACH | 1 | $157,250 | $232,000 |
| 9 | Concrete EV charging equipment foundations (1999-9Z90000J) | SF | 124 | $330.00 | $816.25 |
| 10 | Concrete wheel stops (1999-9Z90000E) | EACH | 26 | $650.00 | $415.76 |
| 11 | Perforated steel square tube slip base sign supports (0930-0114000A) | LB | 252.20 | $15.86 | $4.94 |
| 12 | Furnish level 2 EV chargers, roseburg (1999-9Z90000E) | EACH | 2 | $25,000 | $32,000 |
| 13 | Furnish level 2 EV chargers, ontario (1999-9Z90000E) | EACH | 2 | $25,000 | $32,000 |
| 14 | Furnish level 2 EV chargers, lakeview (1999-9Z90000E) | EACH | 1 | $25,000 | $35,000 |
| 15 | Level 2, 1/2 inch ACP mixture (0744-0202000M) | TON | 61 | $650.00 | $552.11 |
| 16 | Removal of structures and obstructions (0310-0106000A) | LS | 1 | $8,250.00 | $30,000 |
| 17 | Lead compliance plan (0294-0500000A) | LS | 1 | $250.00 | $3,000.00 |
| 18 | Furnish level 2 EV chargers, astoria (1999-9Z90000E) | EACH | 1 | $25,000 | $33,855 |
| 19 | General excavation (0330-0105000K) | CY | 79 | $175.00 | $250.88 |
| 20 | Signs, standard sheeting, plywood (0940-0203000J) | SF | 9 | $140.00 | $107.00 |
| 21 | Furnish level 2 EV chargers, LA grande (1999-9Z90000E) | EACH | 2 | $25,000 | $33,000 |
| 22 | Bollards (0815-0100000E) | EACH | 65 | $1,380.00 | $3,200.00 |
| 23 | Aggregate base (0640-0100000M) | TON | 71 | $250.00 | $157.62 |
| 24 | Concrete curbs, standard curb (0759-0110000F) | LF | 60 | $150.00 | $429.88 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Bid Data Program yearly workbooks. ODOT publishes rank and unit price only: no bidder names and no bid totals, so these bids cannot be checked against a total and Oregon is left out of the competitor views.
Every contract let that day: ODOT letting of September 25, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.