ODOT contract 15609 bid tabulation

Odot fleet charging equipment. Let by Oregon DOT on September 25, 2025, Region 4. 2 bids received.

Owner
Oregon DOT
Letting
25 SEP 2025
Pay items
24
Data through
13 AUG 2026

Bidders

RankTotal bidAgainst the low bid
1Low
2
ODOT contract 15609: bids by rank

Bid tabulation

LinePay itemUnitQuantityRank 1Rank 2
1Longitudinal pavement markings - paint (0860-0200000F)LF200$15.00$39.37
2Asphalt pavement sawcutting, 6 inches deep (0310-0119100F)LF760$10.00$5.00
3Sign support footings (0920-0100000A)CY0.40$17,500$5,214.97
4Furnish level 2 EV chargers, corvallis (1999-9Z90000E)EACH1$25,000$35,000
5Furnish DCFC EV chargers, bend (1999-9Z90000E)EACH1$157,250$232,000
6Furnish level 2 EV chargers, bend (1999-9Z90000E)EACH2$25,000$33,000
7Pollution control plan (0290-0100000A)LS1$500.00$3,000.00
8Furnish DCFC EV chargers, roseburg (1999-9Z90000E)EACH1$157,250$232,000
9Concrete EV charging equipment foundations (1999-9Z90000J)SF124$330.00$816.25
10Concrete wheel stops (1999-9Z90000E)EACH26$650.00$415.76
11Perforated steel square tube slip base sign supports (0930-0114000A)LB252.20$15.86$4.94
12Furnish level 2 EV chargers, roseburg (1999-9Z90000E)EACH2$25,000$32,000
13Furnish level 2 EV chargers, ontario (1999-9Z90000E)EACH2$25,000$32,000
14Furnish level 2 EV chargers, lakeview (1999-9Z90000E)EACH1$25,000$35,000
15Level 2, 1/2 inch ACP mixture (0744-0202000M)TON61$650.00$552.11
16Removal of structures and obstructions (0310-0106000A)LS1$8,250.00$30,000
17Lead compliance plan (0294-0500000A)LS1$250.00$3,000.00
18Furnish level 2 EV chargers, astoria (1999-9Z90000E)EACH1$25,000$33,855
19General excavation (0330-0105000K)CY79$175.00$250.88
20Signs, standard sheeting, plywood (0940-0203000J)SF9$140.00$107.00
21Furnish level 2 EV chargers, LA grande (1999-9Z90000E)EACH2$25,000$33,000
22Bollards (0815-0100000E)EACH65$1,380.00$3,200.00
23Aggregate base (0640-0100000M)TON71$250.00$157.62
24Concrete curbs, standard curb (0759-0110000F)LF60$150.00$429.88
ODOT contract 15609: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Bid Data Program yearly workbooks. ODOT publishes rank and unit price only: no bidder names and no bid totals, so these bids cannot be checked against a total and Oregon is left out of the competitor views.

Every contract let that day: ODOT letting of September 25, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy