SCDOT contract 5370010 bid tabulation
District 3, Package 5 C&LR Bridge Repairs. Let by South Carolina DOT on August 12, 2025, Greenville, Pickens, Spartanburg, District 3. 4 bids received; low bid $1,779,676 by United Infrastructure Group, Inc..
- Owner
- South Carolina DOT
- Letting
- 12 AUG 2025
- Pay items
- 34
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | United Infrastructure Group, Inc. | $1,779,676 | Low |
| 2 | Ipc Paving LLC | $1,781,922 | 0.0% |
| 3 | Cekra, Inc. | $1,893,619 | +6.0% |
| 4 | Freyssinet, Inc. | $2,315,645 | +30% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. United Infrastructure Group, Inc. | 2. Ipc Paving LLC | 3. Cekra, Inc. | 4. Freyssinet, Inc. |
|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $88,984 | $89,000 | $100,000 | $115,000 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $53,390 | $35,620 | $40,000 | $25,000 |
| 0030 | Removal & disposal of designated portions of existing bridge (2028200) | LS | 1 | $353,112 | $40,000 | $6,000.00 | $28,500 |
| 0040 | Liquid asphalt binder PG64-22 (4011004) | TON | 13 | $650.00 | $625.00 | $700.00 | $975.00 |
| 0050 | Milling existing asphalt pavement 2.0" (4013120) | SY | 706 | $25.00 | $52.00 | $58.00 | $81.00 |
| 0060 | Milling existing asphalt pavement 10.0" (4013200) | SY | 180 | $1.00 | $157.00 | $165.00 | $245.00 |
| 0070 | Asphalt surface course type B (4040320) | TON | 218 | $180.00 | $524.00 | $540.00 | $815.00 |
| 0080 | Traffic control (6011000) | LS | 1 | $150,000 | $55,000 | $85,000 | $56,100 |
| 0090 | Barricade - type III (6041200) | LF | 324 | $25.00 | $21.00 | $35.00 | $34.00 |
| 0100 | Permanent construction signs (ground mounted) (6051120) | SF | 2,017 | $6.15 | $7.40 | $14.00 | $11.00 |
| 0110 | Permanent construction signs (barricade mounted) (6051125) | SF | 523 | $8.75 | $8.00 | $8.00 | $11.00 |
| 0120 | Construction zone electric changeable message sign (trailer (6062000) | EACH | 6 | $6,400.00 | $2,500.00 | $4,500.00 | $9,350.00 |
| 0130 | Type B - flashing light (608100B) | EACH | 72 | $165.00 | $125.00 | $125.00 | $150.00 |
| 0140 | Pavement markings(temporary-paint)-4" white solid lines (609115A) | LF | 980 | $0.50 | $0.50 | $0.20 | $0.80 |
| 0150 | Pavement markings(temporary-paint)-4" yellow solid lines (609115B) | LF | 980 | $0.50 | $0.50 | $0.20 | $0.80 |
| 0160 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 980 | $2.50 | $2.50 | $2.00 | $4.00 |
| 0170 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 980 | $2.50 | $2.50 | $2.00 | $4.00 |
| 0180 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 6 | $20.00 | $8.50 | $10.00 | $155.00 |
| 0190 | Conc. for structures - class 4000 (7011400) | CY | 11 | $4,000.00 | $4,900.00 | $10,000 | $24,000 |
| 0200 | Spall repair (7013400) | SF | 86 | $125.00 | $515.00 | $400.00 | $215.00 |
| 0210 | Reinf. steel for structures (bridge) (7031200) | LB | 1,354 | $3.50 | $4.65 | $4.00 | $3.50 |
| 0220 | Treated structural timber (7061100) | MBF | 0.16 | $100,000 | $187,000 | $10,000 | $198,000 |
| 0230 | Structural steel (7091120) | LB | 3,596 | $20.00 | $27.00 | $18.00 | $29.00 |
| 0240 | Concrete curb (9" X 15") (7201000) | LF | 60 | $150.00 | $245.00 | $100.00 | $540.00 |
| 0250 | Removal of epoxy, asphalt & foreign overlay (7260100) | SY | 854 | $35.00 | $75.00 | $80.00 | $23.00 |
| 0260 | Polymer modified asphalt expansion joint (7261210) | LF | 232 | $375.00 | $275.00 | $650.00 | $200.00 |
| 0270 | Waterproofing (bridge deck) (7283000) | SY | 94 | $20.00 | $215.00 | $12.00 | $170.00 |
| 0280 | Rip-rap (class B) (8041020) | TON | 60 | $200.00 | $345.00 | $500.00 | $190.00 |
| 0290 | Geotextile for erosion control under riprap(class 1)type A (8048100) | SY | 55 | $6.00 | $40.00 | $15.00 | $99.00 |
| 0300 | Demo existing pile encasement (8990010) | EACH | 1 | $4,000.00 | $3,300.00 | $6,000.00 | $3,860.00 |
| 0310 | Bridge pile wrap (8990017) | LF | 294 | $700.00 | $680.00 | $950.00 | $1,040.00 |
| 0320 | Cleaning & painting existing steel piling (8990026) | EACH | 24 | $7,500.00 | $6,255.00 | $5,500.00 | $15,500 |
| 0330 | Ultra high performance concrete (uhpc) overlay (8990046) | CY | 6 | $2,500.00 | $20,245 | $8,000.00 | $2,740.00 |
| 0340 | Carbon fiber reinforced polymer (CFRP) laminate (8990048) | EACH | 1,180 | $250.00 | $362.00 | $375.00 | $365.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of August 12, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.