Mobilization (severe damage to guardrail), SCDOT 1031030

Low bidders on SCDOT contracts carried a median of $1.00 per EACH for this item, over the 24 months to 13 OCT 2026, across 28 low bids. Half of all 71 bids fell between $1.00 and $1.00.

Owner
South Carolina DOT
Item
1031030
Unit
EACH
Data through
13 OCT 2026
$1.00Low bidder's median, per EACH
$1.00Median of all bids, per EACH
29Contracts in the window

By year of letting

Mobilization (severe damage to guardrail), SCDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20221414$1.0015$1.00
20231414$1.0028$250.50
20241414$1.0016$1.00
20251514$1.0029$1.00
20261414$1.0042$1.00

Bid prices as published, not adjusted for inflation.

By quantity

Quantity (EACH)Low bidsLow-bid median
22 to 717$1.00
71 to 1167$1.00
121 to 1927$1.00
192 to 2997$1.00
Mobilization (severe damage to guardrail), SCDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
Bagwell Fence Company, Inc.4444 (100%)
Reynolds Fence & Guardrail, Inc.4314 (33%)
The Sharon Company, Inc.1413 (93%)
Mobilization (severe damage to guardrail), SCDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
09 JUN 20265177040District 2215$1.00$1.003The Sharon Company, Inc.SCDOT
09 JUN 20265177110District 2134$1.00$1.003The Sharon Company, Inc.SCDOT
09 JUN 20265277050District 2159$1.00$1.003The Sharon Company, Inc.SCDOT
09 JUN 20265277120District 2192$1.00$1.003The Sharon Company, Inc.SCDOT
09 JUN 20265377060District 2295$1.00$1.003Bagwell Fence Company, Inc.SCDOT
09 JUN 20265377130District 2299$1.00$1.003Bagwell Fence Company, Inc.SCDOT
09 JUN 20265477070District 271$0.75$1.003Bagwell Fence Company, Inc.SCDOT
09 JUN 20265477140District 222$1.00$1.003Bagwell Fence Company, Inc.SCDOT
09 JUN 20265577080District 272$1.00$1.003The Sharon Company, Inc.SCDOT
09 JUN 20265577150District 299$1.00$1.003The Sharon Company, Inc.SCDOT
09 JUN 20265677090District 2121$1.00$1.003Bagwell Fence Company, Inc.SCDOT
09 JUN 20265677160District 2116$1.00$1.003The Sharon Company, Inc.SCDOT
09 JUN 20265777100District 260$1.00$1.003The Sharon Company, Inc.SCDOT
09 JUN 20265777170District 228$1.00$1.003The Sharon Company, Inc.SCDOT
09 DEC 20258875490Statewide1,000n/a$1.001The Sharon Company, Inc.SCDOT
Latest SCDOT contracts carrying Mobilization (severe damage to guardrail)

Filter this item by your own quantity, district and period, or check your price against it, in the SCDOT explorer.

How these prices were read

SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are SCDOT's own: this item is compared with SCDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the SCDOT letting of 13 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy